The Eggborough Gas Fired Generating Station Order 2018

Notice of worksE+W

23.  The undertaker must give to the engineer 30 days' notice of its intention to commence the construction of any of the specified or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, CRT may where appropriate arrange for the publication of notices bringing those works to the attention of users of CRT's network.