15.—(1) Vibro piling must be used as standard, with percussive piling only used if required to drive a pile to its design depth. If percussive piling is necessary soft-start procedures must be used to ensure incremental increase in pile power over a set time period until full operational power is achieved.
(2) The soft-start duration must be a period of not less than twenty minutes.
(3) Should piling cease for a period greater than ten minutes, then the soft start procedure must be repeated.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: