PART 3Review of Requirements as to Frequencies, Timings and Maximum Fares

Failure of lead authority to review requirements as to maximum fares19.

(1)

If a lead authority fails to issue a review notice before the end of the maximum fares requirement period, any participating operator to whom requirements as to maximum fares apply may request a review of the requirements.

(2)

An operator who wishes to make a request under paragraph (1) must make the request in writing and serve it on the lead authority within a period of 28 days beginning with the day on which the maximum fares requirement period ends.

(3)

A copy of the request made under paragraph (1) must, at the same time as the request is served on the lead authority, be sent to a traffic commissioner.

(4)

If, within a period of 14 days beginning with the day on which a request made in accordance with paragraph (1) is received, the lead authority has not issued a review notice, any requirements as to the maximum fares that may be charged for particular journeys, or for journeys of particular descriptions, cease to have effect.

(5)

If a lead authority fails to issue a review notice before the end of the maximum fares requirement period, and no request is made under paragraph (1), any requirements as to the maximum fares that may be charged for particular journeys, or for journeys of particular descriptions, remain in force until, following a subsequent review—

(a)

revised requirements come into effect, or

(b)

the requirements cease to have effect.