The Silvertown Tunnel Order 2018

Consents, agreements and approvalsE+W+S

69.—(1) Where any application is made to a relevant authority, the consent, agreement or approval concerned must, if given, be given in writing and is not to be unreasonably withheld or delayed.

(2) If a relevant authority which has received an application fails to notify TfL of its decision before the end of the period of 28 days beginning with the date on which the application was received, the relevant authority is deemed to have given its consent, agreement or approval, as the case may be.

(3) Any application to which this article applies must include a written statement that the provisions of paragraph (2) apply to that application.

(4) In this article—

application” means an application or request for any consent, agreement or approval required or contemplated by articles 6 (street works), 8 (construction and maintenance of new, altered or diverted streets), 10 (temporary stopping up and restriction of use of streets), 11 (access to works), 16 (authority to survey and investigate land) and 61 (traffic regulation measures); and

relevant authority” means a planning authority, a traffic authority, a highway authority or a street authority.