Search Legislation

The Silvertown Tunnel Order 2018

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes to legislation:

There are currently no known outstanding effects for the The Silvertown Tunnel Order 2018, PART 3 . Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 3 E+W+SPOWERS OF ACQUISITION AND POSSESSION OF LAND

Powers of acquisitionE+W+S

Compulsory acquisition of landE+W+S

19.—(1) TfL may acquire compulsorily so much of the Order land as is required for the authorised development, or to facilitate it, or as is incidental to it.

(2) This article is subject to article 22(2) (compulsory acquisition of rights), article 27(2) (acquisition of subsoil, etc., only) and article 29 (temporary use of land for carrying out the authorised development).

Compulsory acquisition of land – incorporation of the minerals codeE+W+S

20.  Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981 are incorporated into this Order subject to the modifications that—

(a)paragraph 8(3) is not incorporated; and

(b)for “the acquiring authority” substitute “ TfL ”.

Time limit for exercise of powers to possess land temporarily or to acquire land compulsorilyE+W+S

21.—(1) After the end of the period of 5 years beginning with the day on which this Order comes into force—

(a)no notice to treat is to be served under Part 1 (compulsory purchase under Acquisition of Land Act of 1946) of the 1965 Act; and

(b)no declaration is to be executed under section 4 (execution of declaration) of the 1981 Act as applied by article 26 (application of the 1981 Act),

in relation to any part of the Order land.

(2) The authority conferred by article 29 (temporary use of land for carrying out the authorised development) ceases at the end of the period referred to in paragraph (1), except that nothing in this paragraph prevents TfL from remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

Compulsory acquisition of rightsE+W+S

22.—(1) Subject to paragraphs (2), (3) and (5), TfL may acquire such rights over the Order land or impose restrictive covenants affecting the land as may be required for any purpose for which that land may be acquired under article 19 (compulsory acquisition of land), by creating them as well as acquiring rights already in existence.

(2) In the case of the Order land specified in columns (1) and (2) of Schedule 4 (land in which only new rights etc., may be acquired) TfL's powers of compulsory acquisition are limited to the acquisition of such wayleaves, easements, new rights in the land or the imposition of restrictive covenants as TfL may require for or in connection with the authorised development.

(3) Subject to Schedule 2A M1 (counter-notice requiring purchase of land) to the 1965 Act (as substituted by [F1paragraph 5(8)] of Schedule 5 (modification of compensation and compulsory purchase enactments for creation of new rights), where TfL acquires a right over land or the benefit of a restrictive covenant , TfL is not required to acquire a greater interest in that land.

(4) Schedule 5 has effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application to the compulsory acquisition under this article of a right over land by the creation of a new right or the imposition of a restrictive covenant.

(5) TfL may not under paragraph (1) impose restrictive covenants affecting the land situated within any of the Regions mentioned in article 52.

Textual Amendments

Marginal Citations

M1As inserted by paragraphs 1 and 3 of Schedule 17 to the Housing and Planning Act 2016 (c. 22).

Private rights over landE+W+S

23.—(1) Subject to the provisions of this article, all private rights over land subject to compulsory acquisition under this Order are extinguished—

(a)from the date of acquisition of the land by TfL, whether compulsorily or by agreement; or

(b)on the date of entry onto the land by TfL under section 11(1) (powers of entry) of the 1965 Act,

whichever is the earlier.

(2) Subject to the provisions of this article, all private rights over land subject to the compulsory acquisition of rights or the imposition of restrictive covenants under this Order are extinguished in so far as their continuance would be inconsistent with the exercise of the right or burden of the restrictive covenant—

(a)from the date of the acquisition of the right or the benefit of the restrictive covenant by TfL, whether compulsorily or by agreement; or

(b)on the date of entry onto the land by TfL under section 11(1) of the 1965 Act (power of entry),

whichever is the earlier.

(3) Subject to the provisions of this article, all private rights over any part of the Order land that is vested in or acquired by TfL are extinguished on commencement of any activity authorised by this Order which interferes with or breaches those rights.

(4) Subject to the provisions of this article, all private rights over land of which TfL takes temporary possession under this Order are suspended and unenforceable for as long as TfL remains in lawful possession of the land.

(5) Any person who suffers loss by the extinguishment or suspension of any private right or by the imposition of any restrictive covenant under this article is entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(6) This article does not apply in relation to any right to which section 138 (extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) of the 2008 Act or article 31 (statutory undertakers) applies.

(7) Paragraphs (1) to (4) have effect subject to—

(a)any notice given by TfL before—

(i)the completion of the acquisition of the land or the acquisition of the rights or the imposition of restrictive covenants over or affecting the land;

(ii)TfL's appropriation of it;

(iii)TfL's entry onto it; or

(iv)TfL's taking temporary possession of it,

that any or all of those paragraphs do not apply to any right specified in the notice; and

(b)any agreement made at any time between TfL and the person in or to whom the right in question is vested or belongs.

(8) If any such agreement as is referred to in paragraph (7)(b)—

(a)is made with a person in or to whom the right is vested or belongs; and

(b)is expressed to have effect also for the benefit of those deriving title from or under that person,

it is effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement.

(9) References in this article to private rights over land include any right of way, trust, incident, easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support and include restrictions as to the user of land arising by virtue of a contract, agreement or undertaking having that effect.

Power to override easements and other rightsE+W+S

24.—(1) Any authorised activity which takes place on land within the Order limits (whether the activity is undertaken by TfL or by any person deriving title from TfL or by any contractors, servants or agents of TfL) is authorised by this Order if it is done in accordance with the terms of this Order, notwithstanding that it involves—

(a)an interference with an interest or right to which this article applies; or

(b)a breach of a restriction as to the user of land arising by virtue of a contract.

(2) In this article “authorised activity” means—

(a)the erection, construction or maintenance of any part of the authorised development;

(b)the exercise of any power authorised by this Order; or

(c)the use of any land (including the temporary use of land).

(3) The interests and rights to which this article applies include any easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support and include restrictions as to the user of land arising by the virtue of a contract.

(4) Where an interest, right or restriction is overridden by paragraph (1), compensation—

(a)is payable under section 7 (measure of compensation in case of severance) or section 10 (further provision as to compensation for injurious affection) of the 1965 Act; and

(b)is to be assessed in the same manner and subject to the same rules as in the case of other compensation under those sections where—

(i)the compensation is to be estimated in connection with a purchase under that Act; or

(ii)the injury arises from the execution of works on or use of land acquired under that Act.

(5) Where a person deriving title under TfL by whom the land in question was acquired—

(a)is liable to pay compensation by virtue of paragraph (4); and

(b)fails to discharge that liability,

the liability is enforceable against TfL.

(6) Nothing in this article is to be construed as authorising any act or omission on the part of any person which is actionable at the suit of any person on any grounds other than such an interference or breach as is mentioned in paragraph (1) of this article.

Modification of Part 1 of the 1965 ActE+W+S

25.—(1) Part 1 of the 1965 Act, as applied to this Order by section 125 (application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.

(2) In section 4A(1) M2 (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 4” substitute “ section 118 of the Planning Act 2008 (legal challenges relating to applications for orders granting development consent), the five year period mentioned in article 21 (time limit for exercise of powers to possess land temporarily or to acquire land compulsorily) of the Silvertown Tunnel Order 2018 M3.

(3) In section 11A M4 (powers of entry: further notice of entry)—

(a)in subsection (1)(a), after “land” insert “ under that provision ”;

(b)in subsection (2), after “land” insert “ under that provision ”.

(4) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “ article 21 of the Silvertown Tunnel Order 2018 ”.

(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a)for paragraphs 1(2) and 14(2) substitute—

(2) But see article 27(4) (acquisition of subsoil, etc., only) of the Silvertown Tunnel Order 2018, which excludes the acquisition of subsoil or airspace only from this Schedule; and

(b)after paragraph 29, F2... insert—

PART 4E+W+SINTERPRETATION

30.  In this Schedule, references to entering on and taking possession of land do not include doing so under article 15 (protective works to buildings), 29 (temporary use of land for carrying out the authorised development) or 30 (temporary use of land for maintaining the authorised development) of the Silvertown Tunnel Order 2018.

Textual Amendments

Marginal Citations

M2As inserted by section 202(1) of the Housing and Planning Act 2016 (c. 22).

M4As inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).

Application of the 1981 ActE+W+S

26.—(1) The 1981 Act applies as if this Order were a compulsory purchase order.

(2) The 1981 Act, as applied by paragraph (1), has effect with the following modifications.

(3) In section 1 (application of Act) for subsection (2) substitute—

(2) This section applies to any Minister, any local or other public authority or any other body or person authorised to acquire land by means of a compulsory purchase order.

(4) In section 5 (earliest date for execution of declaration), in subsection (2), omit the words from “, and this subsection” to the end.

(5) Omit section 5A M5 (time limit for general vesting declaration).

(6) In section 5B M6 (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 5A” substitute “ section 118 M7 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008, the five year period mentioned in article 21 of the Silvertown Tunnel Order 2018 ”.

(7) In section 6 M8 (notices after execution of declaration), in subsection (1)(b), for “section 15 of, or paragraph 6 of Schedule 1 to, the Acquisition of Land Act 1981” substitute “ section 134 M9 (notice of authorisation of compulsory acquisition) of the Planning Act 2008 ”.

(8) In section 7 (constructive notice to treat) in subsection (1)(a), omit “(as modified by section 4 of the Acquisition of Land Act 1981)”.

(9) In Schedule A1 M10 (counter-notice requiring purchase of land not in general vesting declaration), for paragraph 1(2) substitute—

(2) But see article 27(4) (acquisition of subsoil, etc., only) of the Silvertown Tunnel Order 2018 M11, which excludes the acquisition of subsoil or airspace only from this Schedule.

(10) References to the 1965 Act in the 1981 Act are to be construed as references to the 1965 Act as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and as modified by article 25 (modification of Part 1 of the [F31965 Act])) to the compulsory acquisition of land under this Order.

Textual Amendments

Marginal Citations

M5As inserted by section 182(2) of the Housing and Planning Act 2016 (c. 22).

M6As inserted by section 202(2) of the Housing and Planning Act 2016 (c. 22).

M7As amended by paragraphs 1 and 59 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20) and section 92(4) of the Criminal Justice and Courts Act 2015 (c. 2).

M8As amended by paragraph 52(2) of Schedule 2 to the Planning (Consequential Provisions) Act 1990 (c. 11) and paragraph 7 of Schedule 15 to the Housing and Planning Act 2016 (c. 22).

M9As amended by section 142 of, and Part 21 of Schedule 25 to, the Localism Act 2011 (c. 20) and S.I. 2017/16.

M10As inserted by paragraph 6 of Schedule 18 to the Housing and Planning Act 2016 (c. 22).

Acquisition of subsoil, etc., onlyE+W+S

27.—(1) TfL may acquire compulsorily so much of, or such rights over, the subsoil of and airspace over the land referred to in paragraph (1) of article 19 (compulsory acquisition of land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.

(2) In the case of the Order land specified in columns (1) and (2) of Schedule 6 (land in which only subsoil or new rights above subsoil and surface may be acquired) TfL's powers of compulsory acquisition under article 19 are limited to—

(a)the acquisition of such subsoil; and

(b)the acquisition of such easements or other new rights and the imposition of restrictive covenants in the remaining subsoil and the surface of the land,

as TfL may require for or in connection with the authorised development.

(3) Where TfL acquires any part of, or rights over, the subsoil or surface of or airspace over land referred to in paragraphs (1) or (2), TfL is not required to acquire an interest in any other part of the land.

(4) The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil or airspace only—

(a)Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act;

(b)Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and

(c)section 153(4A) (blighted land: proposed acquisition of part interest; material detriment test) of the Town and Country Planning Act 1990.

(5) Paragraphs (3) and (4) are to be disregarded where TfL acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory or airspace above a house, building or manufactory.

(6) References in paragraph (2)(a) to subsoil are references to the subsoil lying at and below the depths specified in column (3) of Schedule 6 beneath the level of the surface of the land, and references to the remaining subsoil in paragraph (2)(b) are references to the part of the subsoil lying above the shallowest part of the subsoil acquired under paragraph (2)(a) but below the level of the surface of the land.

(7) For the purposes of paragraph (6) “the level of the surface of the land” means—

(a)in the case of any land on which a building is erected, the level of the surface of the ground adjoining the building;

(b)in the case of a river, dock, canal, navigation, watercourse or other water area, the level of the surface of the ground covered by water; or

(c)in any other case, ground surface level,

at the time of this Order coming into force.

Rights over or under streetsE+W+S

28.—(1) TfL may enter on, appropriate and use so much of the subsoil of, or airspace over, any street within the Order limits as may be required for the purposes of the authorised development.

(2) Subject to paragraph (3), TfL may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.

(3) Paragraph (2) does not apply in relation to—

(a)any subway or underground building; or

(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(4) Subject to paragraph (5), any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without TfL acquiring any part of that person's interest in the land, and who suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Temporary possession of landE+W+S

Temporary use of land for carrying out the authorised developmentE+W+S

29.—(1) TfL may, in connection with the carrying out of the authorised development but subject to article 21(1) (time limit for exercise of powers to possess land temporarily or to acquire land compulsorily)—

(a)enter on and take temporary possession of—

(i)the land specified in columns (1) and (2) of Schedule 7 (land of which only temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule relating to the part of the authorised development specified in column (4) of that Schedule; and

(ii)any of the Order land in respect of which no notice of entry has been served under section 11 M12(powers of entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 M13 (execution of declaration) of the 1981 Act;

(b)remove any buildings and vegetation from that land;

(c)construct temporary works (including the provision of means of access) and buildings on that land;

(d)construct any works on that land as are mentioned in Schedule 1 (authorised development); and

(e)provide any temporary car parking or storage facilities on that land for the benefit of landowners or occupiers temporarily displaced as a result of the carrying out of the authorised development.

(2) TfL's temporary possession of any part of the river Thames under paragraph (1) is limited to what is reasonably necessary for TfL safely to construct the authorised development but TfL is not permitted by this article to take temporary possession of the entire width of the river Thames within the Order limits except in an emergency.

(3) At times and places where TfL has taken temporary possession of any part of the river Thames under this article, on the coming into effect of a notice to mariners in accordance with article 17(7) (work in the river Thames: conditions), the public right of navigation over that part of the river Thames is suspended and unenforceable against the PLA.

(4) Any person who suffers loss as a result of the suspension of any private right of navigation under this article is entitled to be paid compensation for such loss by TfL, to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Not less than 14 days before entering on and taking temporary possession of land under this article TfL must serve notice of the intended entry on the owners and occupiers of the land and that notice must state the works, facilities or other purpose for which TfL intends to take possession of the land.

(6) TfL may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a)in the case of any land specified in paragraph (1)(a)(i), after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (4) of Schedule 7; or

(b)in the case of any land referred to in paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of completion of the works, use of facilities or other purpose for which temporary possession of the land was taken unless TfL has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.

(7) Before giving up possession of land of which temporary possession has been taken under this article, TfL must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but TfL is not required to—

(a)replace a building removed under this article;

(b)restore the land on which any permanent works have been constructed under paragraph (1)(d);

(c)remove any ground strengthening works which have been placed on the land to facilitate construction of the authorised development; or

(d)remove any measures installed over or around statutory undertakers' apparatus to protect that apparatus from the authorised development.

(8) TfL must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(9) Any dispute as to a person's entitlement to compensation under paragraph (8), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(10) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (8) and nothing in this article affects any liability to pay compensation to the PLA under paragraph 49 of Schedule 13 (protective provisions).

(11) Where TfL takes possession of land under this article, TfL is not required to acquire the land or any interest in it.

(12) Section 13 M14 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

Marginal Citations

M12As amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.

M13As amended by section 184 and 185 of, and paragraphs 1 and 2 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).

M14As amended by sections 62(3) and 139 of, and paragraph 27 and 28 of Schedule 13, and part 3 of Schedule 23, to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).

Temporary use of land for maintaining the authorised developmentE+W+S

30.—(1) Subject to paragraph (5), at any time during the maintenance period relating to any of the authorised development, TfL may—

(a)enter upon and take temporary possession of any land within the Order limits if possession is reasonably required for the purpose of maintaining the authorised development;

(b)enter on any land within the Order limits for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development; and

(c)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) TfL's temporary possession of any part of the river Thames under paragraph (1) is limited to what is reasonably necessary for TfL safely to carry out any maintenance of the authorised development but TfL is not permitted by this article to take temporary possession of the entire width of the river Thames within the Order limits except in an emergency.

(3) At times and places where TfL has taken temporary possession of any part of the river Thames under this article, on the coming into effect of a notice to mariners in accordance with article 17(7) (work in the river Thames: conditions) the public right of navigation over that part of the river Thames will be suspended and unenforceable against the PLA.

(4) Any person who suffers loss as a result of the suspension of any private right of navigation under this article is entitled to be paid compensation for such loss by TfL, to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Paragraph (1) does not authorise TfL to take temporary possession of—

(a)any house or garden belonging to a house; or

(b)any building (other than a house) if it is for the time being occupied.

(6) Not less than 28 days before entering upon and taking temporary possession of land under this article TfL must serve notice of the intended entry on the owners and occupiers of the land and that notice must state the purpose for which TfL intends to take possession of the land including the particulars of the part of the authorised development for which possession is to be taken.

(7) TfL may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.

(8) Before giving up possession of land of which temporary possession has been taken under this article, TfL must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(9) TfL must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(10) Any dispute as to a person's entitlement to compensation under paragraph (9), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(11) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (9) and nothing in this article affects any liability to pay compensation to the PLA under paragraph 49 of Schedule 13 (protective provisions).

(12) Where TfL takes possession of land under this article, it is not required to acquire the land or any interest in it.

(13) Section 13 (refusal to give possession to the acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(14) In this article “the maintenance period”, in relation to any part of the authorised development, means the period of 5 years beginning with the date on which—

(a)that part of the authorised development is first opened for public use (where that part of the authorised development is intended to be used by the public); or

(b)in respect of any other part of the authorised development, that part is first brought into operational use by TfL.

SupplementaryE+W+S

Statutory undertakersE+W+S

31.—(1) Subject to the provisions of article 22(2) (compulsory acquisition of rights), Schedule 13 (protective provisions) and paragraph (2), TfL may—

(a)exercise the powers conferred by articles 19 (compulsory acquisition of land) and 22 (compulsory acquisition of rights) in relation to so much of the Order land as belongs to statutory undertakers; and

(b)extinguish the rights of, remove or reposition the apparatus belonging to statutory undertakers over or within the Order land.

(2) Paragraph (1)(b) has no effect in relation to apparatus in respect of which the following provisions apply—

(a)Part 3 (street works in England and Wales) of the 1991 Act; or

(b)article 32 (apparatus and rights of statutory undertakers in stopped up streets).

Apparatus and rights of statutory undertakers in stopped up streetsE+W+S

32.—(1) Where a street is stopped up under article 9 (permanent stopping up of streets and private means of access), any statutory utility whose apparatus is under, in, on, along or across the street has the same powers and rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not been made.

(2) Where a street is stopped up under article 9 any statutory utility whose apparatus is under, in, on, over, along or across the street may, and if reasonably requested to do so by TfL must—

(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the utility may reasonably determine and have power to place it; or

(b)provide other apparatus in substitution for the existing apparatus and place it in such position as described in sub-paragraph (a).

(3) Subject to the following provisions of this article, TfL must pay to any statutory utility an amount equal to the cost reasonably incurred by the utility in or in connection with—

(a)the execution of the relocation works required in consequence of the stopping up of the street; and

(b)the doing of any other work or thing rendered necessary by the execution of the relocation works.

(4) If in the course of the execution of relocation works under paragraph (2)—

(a)apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or

(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by TfL, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from this paragraph, would be payable to the statutory utility by virtue of paragraph (3) is to be reduced by the amount of that excess.

(5) For the purposes of paragraph (4)—

(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and

(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.

(6) An amount which, apart from this paragraph, would be payable to a statutory utility in respect of works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

(7) Paragraphs (3) to (6) do not apply where the authorised development constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead—

(a)the allowable costs of the relocation works are to be determined in accordance with section 85 (sharing of cost of necessary measures) of that Act and any regulations for the time being having effect under that section; and

(b)the allowable costs are to be borne by TfL and the statutory utility in such proportions as may be prescribed by any such regulations.

(8) In this article—

relocation works” means work executed, or apparatus provided, under paragraph (2); and

statutory utility” means a statutory undertaker for the purposes of the 1990 Act or a public communications provider as defined in section 151(1) (interpretation) of the Communications Act 2003 M15.

Marginal Citations

Recovery of costs of new connectionE+W+S

33.—(1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 31 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from TfL compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 31, any person who is—

(a)the owner or occupier of premises the drains of which communicated with that sewer; or

(b)the owner of a private sewer which communicated with that sewer,

is entitled to recover from TfL compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.

(3) This article does not have effect in relation to apparatus to which article 32 (apparatus and rights of statutory undertakers in stopped up streets) or Part 3 of the 1991 Act applies.

(4) In this article—

public communications provider” has the same meaning as in section 151(1) (interpretation) of the Communications Act 2003; and

public utility undertaker” means a gas, water, electricity or sewerage undertaker.

Special category landE+W+S

34.—(1) On the exercise by TfL of the relevant Order powers, so much of the special category land as is required for the purposes of the exercise of those rights is discharged from all rights, trusts and incidents to which it was previously subject, so far as their continuance would be inconsistent with the exercise of the relevant Order powers.

(2) In this article—

the relevant Order powers” means powers exercisable over the special category land by TfL under article 22 (compulsory acquisition of rights); and

the special category land” means the land identified as forming open space and numbered 03-021, 03-029, 03-037, 03-037b and 03-037c in the book of reference and on the special category land plan.

Disposals by the Greater London AuthorityE+W+S

35.—(1) The following are not to be regarded as a disposal by the GLA for the purposes of section 333ZC M16 (disposal etc of land held for housing and regeneration purposes) of the 1999 Act—

(a)the making of any agreement between TfL and the GLA before this Order comes into force in anticipation of the exercise of the powers of this Order by TfL;

(b)the implementation of any such agreement; and

(c)the exercise of the powers of this Order by TfL in accordance with that agreement.

(2) In this article the GLA includes a company or body through which the GLA exercises functions in relation to housing or regeneration.

(3) Paragraph (1)(a) does not apply to a subsequent variation of any agreement made between TfL and the GLA before this Order comes into force.

Marginal Citations

M16As inserted by section 187(1) and (3) of the Localism Act 2011 (c. 20).

CompensationE+W+S

Disregard of certain interests and improvementsE+W+S

36.—(1) In assessing the compensation payable to any person on the acquisition from that person of any land or right over any land under this Order, the tribunal must not take into account—

(a)any interest in land; or

(b)any enhancement of the value of any interest in land by reason of any building erected, works executed or improvement or alteration made on relevant land,

if the tribunal is satisfied that the creation of the interest, the erection of the building, the execution of the works or the making of the improvement or alteration as part of the authorised development was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.

(2) In paragraph (1) “relevant land” means the land acquired from the person concerned or any other land with which that person is, or was at the time when the building was erected, the works executed or the improvement or alteration made as part of the authorised development, directly or indirectly concerned.

Set-off for enhancement in value of retained landE+W+S

37.—(1) In assessing the compensation payable to any person in respect of the acquisition from that person under this Order of any land (including the subsoil) the tribunal must set off against the value of the land so acquired any increase in value of any contiguous or adjacent land belonging to that person in the same capacity which will accrue to that person by reason of the construction of the authorised development.

(2) In assessing the compensation payable to any person in respect of the acquisition from that person of any new rights over land (including the subsoil) under article 22 (compulsory acquisition of rights), the tribunal must set off against the value of the rights so acquired—

(a)any increase in the value of the land over which the new rights are required; and

(b)any increase in value of any contiguous or adjacent land belonging to that person in the same capacity,

which will accrue to that person by reason of the construction of the authorised development.

(3) The 1961 Act has effect, subject to paragraphs (1) and (2), as if this Order were a local enactment for the purposes of that Act.

No double recoveryE+W+S

38.  Compensation is not payable in respect of the same matter both under this Order and under any other enactment, any contract or any rule of law, or under two or more different provisions of this Order.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources