Work No. 17 – shown on sheet 3 of the works plans and being the works associated with the construction of a Silvertown tunnel services compound in the vicinity of the North Portal (Silvertown), to include—

(a)the construction of tunnel services buildings;

(b)the construction of a new private means of access to the tunnel services compound from the realigned Dock Road (Work No. 18) as shown on sheet 3 of the rights of way and access plans;

(c)the construction of internal access roads and operational parking facilities;

(d)the construction of a drainage attenuation tank and associated infrastructure to the west of the proposed Silvertown Tunnel northern approach (Work No, 15);

(e)the provision of security fencing and bollards; and

(f)the provision of landscaping.