SCHEDULES

SCHEDULE 12DEEMED MARINE LICENCE

PART 2CONDITIONS APPLYING TO CONSTRUCTION ACTIVITIES

Construction method statement5

1

The licence holder must submit a method statement, for approval by the MMO following consultation with the Environment Agency, at least 6 weeks prior to the commencement of any licensed activity.

2

The method statement must include the following details—

a

the detailed construction methodology to be employed by the licence holder in carrying out the licensed activity; and

b

a programme of works including timings and durations, method of delivery of material to site and plant to be used during the works.

3

The licence holder must not commence the licensed activity until the MMO has approved in writing the submitted method statement.

4

The licensed activity must be carried out in accordance with the approved method statement, unless otherwise agreed in writing by the MMO.