SCHEDULE 12DEEMED MARINE LICENCE
PART 2CONDITIONS APPLYING TO CONSTRUCTION ACTIVITIES
Marine pollution contingency plan6
1
The licence holder must submit a marine pollution contingency plan, for approval by the MMO, at least 6 weeks prior to the commencement of any licensed activity.
2
The marine pollution contingency plan must set out the licence holder’s assessment of the likely risks which could arise as a result of a spill or collision during construction and operation of the authorised development and the methods and procedures the licence holder intends to put in place to address them.
3
The MMO must consult the Environment Agency and the PLA on the marine pollution contingency plan before approving it.
4
The licence holder must not commence the licensed activity until the MMO has approved in writing the submitted marine pollution contingency plan.
5
The licensed activity must be carried out in accordance with the approved marine pollution contingency plan, unless otherwise agreed in writing by the MMO.