Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
35.—(1) TfL must undertake the detailed design and construction of the tunnelling works to ensure that, as far as is reasonably foreseeable, the navigable channel of the river Thames can be maintained by the PLA to a depth of at least 5.80 metres below chart datum.
(2) When complying with sub-paragraph (1) TfL must allow for potential ‘over-dredge’ of 0.5 metres attributable to standard dredging methodology.
(3) Prior to commencing construction of the tunnelling works and as soon as reasonably practicable after they each become available, TfL must provide to the PLA the following documents—
(a)an Approval in Principle, or similar, demonstrating that the design requirement has been incorporated into the detailed design of the tunnelling works;
(b)a Design Certificate demonstrating that the detailed design of the tunnelling works has satisfied the design requirement; and
(c)a Check Certificate, completed by an independent person, demonstrating that the detailed design of the tunnelling works has satisfied the design requirement.
(4) TfL must supply to the PLA—
(a)any of the drawings referred to in either of the certificates specified in sub-paragraphs (3)(b) and (3)(c); and
(b)such other information relating to any of the documents provided under sub-paragraph (2) or (3)(a) as the PLA may reasonable require,
upon request made by the PLA within 10 business days of the day on which the PLA receives the document that gives rise to the request.
(5) If, following receipt of any of the documents supplied under sub-paragraphs (3) and (4), the PLA is not reasonably satisfied that the design requirement will be met, it may within 20 business days of the paragraph 35 specified day, notify TfL that the PLA is in dispute with TfL and accordingly refer the matter to arbitration under paragraph 52 to review the proposed detailed design of the tunnelling works so far as it concerns the design requirement.
(6) In this paragraph—
(a)“Approval in Principle”, “Check Certificate” and “Design Certificate” have the same meaning as in the Design Manual for Roads and Bridges Volume 1 Section 1 Part 1 BD2/12;
(b)“the design requirement” means the detailed design requirement specified in sub-paragraphs (1) and (2);
(c)“ ” means Regions 2 and 4 as defined in article 52 (restrictions on other works in the river Thames);
(d)“the paragraph 35 specified day” means—
(i)the day on which the documents referred to in sub-paragraph (3) are provided to the PLA under that sub-paragraph; or
(ii)the day on which TfL provides the PLA with all drawings and further information that has been requested by the PLA under sub-paragraph (4),
whichever is the later.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: