SCHEDULES

SCHEDULE 13E+W+SPROTECTIVE PROVISIONS

PART 1 E+W+SFOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS

6.—(1) If, in the exercise of the powers conferred by this Order, TfL acquires any interest in any land in which any apparatus is placed or over which access to any apparatus is enjoyed or requires that the statutory undertaker's apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule, and any right of a statutory undertaker to maintain that apparatus in that land and to gain access to it must not be extinguished, until alternative apparatus has been constructed and is in operation, and access to it has been provided, to the reasonable satisfaction of the statutory undertaker in question in accordance with sub-paragraphs (2) to (8).E+W+S

(2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, TfL requires the removal of any apparatus placed in that land, TfL must give to the statutory undertaker in question 28 days' written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order a statutory undertaker reasonably needs to remove any of its apparatus) TfL must, subject to sub-paragraph (3), afford to the statutory undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of TfL and subsequently for the maintenance of that apparatus.

(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of TfL, or TfL is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the statutory undertaker in question must, on receipt of a written notice to that effect from TfL, as soon as reasonably practicable use reasonable endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.

(4) The obligation imposed on the statutory undertaker under sub-paragraph (3) does not extend to the exercise by the statutory undertaker of any power to acquire any land or rights in land by compulsory purchase order.

(5) Any alternative apparatus to be constructed in land of TfL under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the statutory undertaker in question and TfL or in default of agreement settled by arbitration in accordance with article 68 (arbitration).

(6) The statutory undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 68 (arbitration), and after the grant to the statutory undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by TfL to be removed under the provisions of this Part of this Schedule.

(7) Regardless of anything in sub-paragraph (6), if TfL gives notice in writing to the statutory undertaker in question that it desires itself to execute any work, or part of any work, in connection with the construction or removal of apparatus in any land controlled by TfL, that work, instead of being executed by the statutory undertaker, may be executed by TfL, with the prior written consent of the statutory undertaker (which must not be unreasonably withheld or delayed and is to be subject to any such conditions as are reasonable and proper to protect the apparatus) in accordance with plans and in a position agreed between the statutory undertaker and TfL or, in default of agreement, determined by arbitration in accordance with article 68 (arbitration), without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the statutory undertaker.

(8) In carrying out any work under sub-paragraph (7) TfL must comply with all statutory obligations which would have been applicable had the works been carried out by the statutory undertaker.

(9) Nothing in sub-paragraph (7) authorises TfL to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 600 millimetres of the apparatus.