SCHEDULES

SCHEDULE 2E+W+SREQUIREMENTS

PART 2 E+W+SPROCEDURE FOR DISCHARGE OF REQUIREMENTS

InterpretationE+W+S

22.  In this Part of this Schedule, “discharging authority” means—

(a)any body responsible for giving any consent, agreement or approval required by a requirement included in Part 1 of this Schedule, or for giving any consent, agreement or approval further to any document referred to in any such requirement; or

(b)the local authority in the exercise of its functions set out in sections 60 (control of noise of construction sites) and 61 (prior consent for work on construction sites) of the Control of Pollution Act 1974 M1.

Marginal Citations

M11974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), Schedule 15 to the Environmental Protection Act 1990 (c. 43) and Schedule 24 to the Environment Act 1995 (c. 25). There are other amendments to section 61 but none are relevant.