The Silvertown Tunnel Order 2018

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Paragraph 7

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Silvertown Tunnel Order 2018, Paragraph 7. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Monitoring and mitigation strategyE+W+S

7.—(1) The provisions of this requirement must be carried out in accordance with the monitoring and mitigation strategy and TfL must otherwise comply with the obligations set out in that document.

(2) If the statutory powers vested in TfL in relation to highways and road traffic in Greater London are not sufficient to enable TfL to implement any mitigation measure which it is obliged to implement under this requirement, TfL must either—

(a)seek to agree with the council of the relevant London borough that TfL may implement that measure on behalf of the council; or

(b)if such an agreement cannot be reached, pay to that council a sum equivalent to—

(i)the estimated cost of the council implementing that measure, which the council must use for that purpose; or

(ii)the costs reasonably incurred by the council in implementing an alternative measure in the same location which the council determines will mitigate the adverse impact attributable to the authorised development,

whichever is less.

(3) In this paragraph, “relevant air quality authority” means the council of a London Borough for an area in relation to which the expert review carried out under sub-paragraph (14) concludes that the authorised development has materially worsened air quality.

Pre-opening traffic measures

(4) Before the Silvertown Tunnel opens for public use TfL must carry out an updated assessment of the likely impacts of the authorised development on the performance of the highway network and must consult the members of STIG on a proposed scheme of mitigation which identifies—

(a)the locations on the highway network where the assessment demonstrates there is likely to be a material worsening of traffic conditions as a result of the operation of the authorised development;

(b)the measures which TfL proposes to mitigate the impacts of such a worsening of traffic conditions; and

(c)the proposed programme for implementation of those measures.

(5) TfL must have regard to any consultation responses received from STIG members and before finalising the scheme of mitigation must liaise further with the council of any London Borough on the detail of mitigation measures which it proposes to implement on roads in that Borough. TfL must then submit the scheme of mitigation to the Secretary of State for approval.

(6) The scheme of mitigation submitted to the Secretary of State for approval must include—

(a)details and locations of the proposed mitigation measures;

(b)responses to the consultation and further liaison carried out under sub-paragraphs (4) and (5);

(c)the estimated cost of implementing each measure; and

(d)the proposed programme for the implementation of those measures.

(7) The Silvertown Tunnel must not open for public use until the scheme of mitigation has been approved by the Secretary of State. If the Secretary of State proposes to approve the scheme of mitigation with material modifications, the Secretary of State must consult the members of STIG on the proposed modifications and have regard to any responses received when deciding whether to approve the scheme.

(8) TfL must implement or secure the implementation of the measures approved by the Secretary of State in accordance with the approved programme.

(9) The Secretary of State may, with the consent of the Mayor of London, delegate their functions under this paragraph to the Mayor of London.

Post-opening monitoring and mitigation

(10) For the duration of the monitoring period, TfL must—

(a)implement a monitoring programme in consultation with the members of STIG;

(b)prepare—

(i)quarterly monitoring reports for a period of one year from the Silvertown Tunnel opening for public use; and

(ii)annual monitoring reports thereafter,

derived from that monitoring, and submit them for consideration by the members of STIG;

(c)identify in consultation with the members of STIG appropriate thresholds for changes on the highway network which require TfL to investigate whether mitigation measures are necessary;

(d)develop in consultation with the relevant highway authority any measures which are necessary to mitigate adverse impacts on the highway network which are attributable to the operation of the authorised development; and

(e)implement or secure the implementation of the necessary mitigation measures.

(11) In sub-paragraph (10) “the monitoring period” means a period commencing not less than three years before the Silvertown Tunnel is expected to open for public use and continuing for not less than three years after the Silvertown Tunnel opens for public use.

Air quality monitoring and mitigation

(12) Not less than three years before the Silvertown Tunnel is expected to open for public use TfL must install Nitrogen Dioxide (“NO2”) monitors at locations determined in accordance with paragraph 3.7.4 of the monitoring and mitigation strategy.

(13) The NO2 monitors must remain in place for the period specified in paragraph 3.7.5 of the monitoring and mitigation strategy.

(14) The monitoring data within each annual monitoring report referred to in sub-paragraph (10) must be reviewed as soon as reasonably practicable by a firm of independent air quality experts appointed by TfL in consultation with the members of STIG. The annual review undertaken by the firm of experts must determine in accordance with the criteria set out in the monitoring and mitigation strategy whether or not there has been a material worsening of air quality as a result of the authorised development beyond the likely impacts reported within the environmental statement at locations where there are (whether as a result of the authorised development of otherwise) exceedances of national air quality objectives.

(15) If the review demonstrates in the opinion of the appointed firm of experts that the authorised development has materially worsened air quality in the manner described in sub-paragraph (14), TfL must—

(a)within three months of the conclusion of the expert review consult any relevant air quality authority on a preliminary scheme of mitigation including a programme for its implementation; and

(b)following that consultation submit a detailed scheme of mitigation to the Mayor of London for approval.

(16) Before considering whether to approve the scheme of mitigation, the Mayor of London must consult any relevant air quality authority and take into consideration any responses received.

(17) TfL must implement or secure the implementation of the scheme of mitigation approved by the Mayor of London in accordance with the programme contained in the approved scheme of mitigation.

[F1Hoola building

(18) No part of the authorised development is to be opened for public use until a scheme of mitigation (which may consist of or include ventilation) to reduce to acceptable levels any exposure to nitrogen dioxide which occurs as a result of the authorised development at the first floor residential accommodation at the Hoola building, has been submitted to and approved by the London Borough of Newham (“Hoola scheme of mitigation”).

(19) TfL must implement the approved Hoola scheme of mitigation.]

Textual Amendments

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources