Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 29

SCHEDULE 7E+W+SLAND OF WHICH ONLY TEMPORARY POSSESSION MAY BE TAKEN

(1) Area(2) Plot Reference Number(s) shown on land plans(3) Purpose for which temporary possession may be taken(4) Relevant part of the authorised development
Royal Borough of Greenwich

01-007, 01-008,

01-011

Working space to facilitate removal of existing gantry.

Work No. 4
01-022, 01-022a, 01-027, 01-027a, 01-050a, 01-057a, 01-057b

Working space to facilitate improvement of Tunnel Avenue and construction of new Boord Street foot and cycle bridge including accommodation works to provide replacement access and replacement car parking for adjacent premises.

Work Nos. 4 and 11
01-044, 01-045

Access to works and working space to facilitate improvement of A102 Blackwall Tunnel Southern Approach, and construction of new Boord Street foot and cycle bridge and temporary diversion of Millennium Way.

Work Nos. 1, 2, 3, 11 and 14
01-045b, 01-083, 01-084, 01-087, 01-087a, 01-090, 02-018, 02-021, 02-022, 02-022a, 02-026

Temporary diversion of Millennium Way and Edmund Halley Way, working space to facilitate construction of Silvertown Tunnel, provision of temporary replacement car parking and associated access and provision of private means of access to premises.

Work Nos. 1 and 12
01-047

Working space to facilitate construction of new Boord Street foot and cycle bridge; new access to premises; and improvement of A102 Blackwall Tunnel Southern Approach.

Work Nos. 2 and 11
01-061, 01-091, 02-045

Working space to facilitate construction of gantry.

Work Nos. 2 and 4
01-077, 01-077a, 01-086, 02-015, 02-016, 02-017

Working space and construction compounds to facilitate construction of Silvertown Tunnel and its southern approach and services compound, and construction of new private means of access.

Work Nos.1, 2, 5, 6 and 12
02-036, 02-051

Working space and construction compounds to facilitate construction of Silvertown Tunnel, new Pavilion Lane and access to statutory undertakers' apparatus.

Work Nos. 1, 5, 6, 10 and 12

02-036b, 02-037,

02-041a, 02-047,

02-050, 02-052,

02-052b, 02-052c

Working space to facilitate construction of new Pavilion Lane and new access to statutory undertakers' apparatus.

Work No. 10
02-043a

Working space and construction compounds to facilitate construction of the Silvertown Tunnel and new Pavilion Lane; and temporary diversion of Millennium Way and Edmund Halley Way.

Work Nos.1,10, 12
02-059, 02-062a, 02-075a

Working space and construction compounds to facilitate construction of Silvertown Tunnel; and temporary diversion of Millennium Way and Edmund Halley Way.

Work No. 1

02-066, 02-067,

02-070, 02-081

Working space to facilitate construction of new Pavilion Lane.

Work No. 9
02-072, 02-073

Working space to facilitate construction of new Pavilion Lane; and temporary diversion of Millennium Way.

Work Nos. 1 and 9
02-078, 02-079, 02-080

Working space to facilitate temporary diversion of Millennium Way.

Work No. 1
02-084, 02-087

Working space to facilitate improvement of the A102 Blackwall Tunnel southern approach and construction of new Pavilion Lane.

Work Nos. 2 and 9
03-002, 03-002b, 03-003, 03-004, 03-005, 03-006

Working space to facilitate temporary diversion of Millennium Way.

Work Nos.1 and 14
03-007, 03-008, 03-017a, 03-019a, 03-020a, 03-021a, 03-026a, 03-028a, 03-030a, 03-037d, 03-037e, 03-037f

Working space and construction compounds to facilitate construction of Silvertown Tunnel; and temporary diversion of Edmund Halley Way.

Work No. 1
03-007a, 03-007b, 03-008a, 03-008b, 03-013, 03-014

Provision of a temporary replacement car park and associated buildings and access.

Work No. 1

03-034, 03-036, 03-044, 04-001, 04-002, 04-003, 04-004

Provision of a temporary replacement car park.Work No. 1
04-026, 04-027

Working space to facilitate river wall works.

Work No. 1
London Borough of Newham04-035, 05-001, 05-004, 05-006, 06-001

Working space to facilitate construction of Silvertown Tunnel and construction of temporary jetty and transportation area, including related dredging works and operations, and the establishment of an exclusion zone for the jetty.

Work Nos. 1, 20A and 20B

05-014, 05-018,

05-019, 05-024,

05-025, 05-026,

05-040, 05-041,

05-042, 05-043,

05-044, 05-045,

05-048, 05-048b, 05-049, 05-050, 05-051, 05-054, 05-060, 05-064, 05-075, 05-081, 05-084, 05-109, 05-111, 06-006,

06-008, 06-009,

06-019, 06-020,

06-032, 06-036,

06-037, 06-042,

06-044, 06-053,

06-054, 06-055

Working space and construction compounds to facilitate construction of Silvertown Tunnel and realigned Dock Road and temporary relocated car parking and access thereto.Work Nos. 1, 17 and 18

05-016, 05-023,

05-028, 05-032,

05-033, 05-035

Working space and construction compounds to facilitate construction of Silvertown Tunnel, realigned Dock Road and temporary jetty and temporary relocated car parking and access to them.

Work Nos. 1, 17, 18, 20A and 20B
05-047, 06-002, 06-003, 06-004, 06-005, 06-007, 06-010, 06-011, 06-012, 06-013, 06-027, 06-033, 06-035, 06-057, 06-060

Working space and construction compounds to facilitate construction of Silvertown Tunnel and realigned Dock Road, and to provide a temporary storage area and related access, and temporary relocated car parking and access to them.

Work Nos. 1, 17 and 18

06-066, 06-068, 06-096, 06-098, 07-006, 07-007a, 07-007, 07-008, 07-009

Working space to facilitate improvement of the existing Tidal Basin Roundabout and Tidal Basin Road.

Work Nos. 16 and 19

06-075, 06-078

Working space to facilitate improvement of the existing Tidal Basin Roundabout and Tidal Basin Road, and temporary relocated car parking and access to them.

Work Nos. 16, 17 and 19
06-093

Working space and construction compounds to facilitate construction of the Silvertown Tunnel and its northern approach and services compound, and temporary relocated car parking and access to them.

Work Nos. 1, 15 and 17

07-029

Working space and construction compounds to facilitate construction of the Silvertown Tunnel and its northern approach and services compound.

Work Nos. 1, 15 and 17

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources