Search Legislation

The Renewable Heat Incentive Scheme Regulations 2018

Changes over time for: CHAPTER 1

 Help about opening options

Alternative versions:

Status:

Point in time view as at 22/05/2018.

Changes to legislation:

There are currently no known outstanding effects for the The Renewable Heat Incentive Scheme Regulations 2018, CHAPTER 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

CHAPTER 1E+W+SOngoing obligations relating to the use of solid biomass to generate heat

InterpretationE+W+S

36.  In this Part—

allocating authority” has the same meaning as in section 24(1) of the Waste and Emissions Trading Act 2003 M1;

landfill gas” means gas formed by the digestion of material in a landfill;

municipal waste” has the same meaning as in section 21 of the Waste and Emissions Trading Act 2003 M2;

standby generation” means the generation of electricity by equipment which is not used frequently or regularly to generate electricity and where all the electricity generated by that equipment is used by the accredited RHI installation;

waste collection authority” has the same meaning as in section 30(3) of the Environmental Protection Act 1990 M3;

waste disposal authority” has the same meaning as in section 30(2) of the Environmental Protection Act 1990 M4.

Marginal Citations

M12003 c.33. Section 24(1) was amended by S.I. 2013/141.

M31990 c.43. Section 30(3) was amended by paragraph 17(3) of Schedule 9 to the Local Government (Wales) Act 1994 (c.19), and subsection (3)(c) was amended by paragraph 167(3) of Schedule 13 to the Local Government etc. (Scotland) Act 1994 (c.39).

M4Section 30(2)(f) was substituted by paragraph 17(2) of Schedule 9 to the Local Government (Wales) Act 1994, and paragraph (g) was amended by paragraph 167(3) of Schedule 13 to the Local Government etc. (Scotland) Act 1994.

Participants using solid biomass contained in wasteE+W+S

37.—(1) This regulation applies to a participant generating heat in an accredited RHI installation from solid biomass contained in waste.

(2) The proportion of solid biomass contained in the waste must be a minimum of 10%.

(3) For the purposes of paragraph (2)—

(a)the proportion of solid biomass contained in the waste is to be determined by the Authority for every quarterly period;

(b)it is for the participant to provide, in such form as the Authority may require, evidence to demonstrate to the Authority's satisfaction the proportion of the energy content of the waste used in any quarterly period which is composed of fossil fuel, to enable the Authority to determine the proportion of solid biomass in accordance with sub-paragraph (c);

(c)the proportion of solid biomass is the energy content of the waste used in any quarterly period to generate heat less the energy content of any fossil fuel of which that waste is in part composed, expressed as a percentage of the energy content of that waste.

(4) The participant may use fossil fuel (other than fossil fuel mentioned in paragraph (3)(c)) in an accredited RHI installation for the following permitted ancillary purposes only—

(a)cleansing other fuels from the accredited RHI installation's combustion system prior to using fossil fuel to heat the combustion system to its normal temperature;

(b)the heating of the accredited RHI installation's combustion system to its normal operating temperature or the maintenance of that temperature;

(c)the ignition of fuels of low or variable calorific value;

(d)emission control;

(e)in relation to accredited RHI installations which are CHP systems, standby generation or the testing of standby generation capacity.

(5) The energy content of the fossil fuel used during any quarterly period for the permitted ancillary purposes specified in paragraph (4) must not exceed 10% of the energy content of all the fuel used by that accredited RHI installation or where the installation is a CHP system, by a combustion unit which supplies energy to that installation from solid biomass contained in waste, to generate heat during that quarterly period.

(6) Without prejudice to paragraph (3)(b), when determining the proportion of solid biomass contained in waste, the Authority may have regard to any information (whether or not produced to it by the participant) if, in its opinion, that information indicates what proportion of the energy content of the waste is composed of fossil fuel.

(7) Where the participant produces to the Authority—

(a)data published by an allocating authority, a waste disposal authority or a waste collection authority, demonstrating that the proportion of municipal waste used by that participant which is composed of fossil fuel is unlikely to exceed 50%; and

(b)evidence that the municipal waste used has not been subject to any process before being used that is likely to have materially increased that proportion,

the Authority may accept this as sufficient evidence for the purposes of paragraph (3)(b) of the fact that the proportion of the municipal waste used which is composed of fossil fuel is no more than 50%.

(8) Where the Authority so requests, the participant must arrange for samples of the waste used (or to be used) in the accredited RHI installation, or of any gas or other substance produced as the result of the use of such waste, to be taken by a person (and analysed in a manner) specified by the Authority, and for the results of that analysis to be made available to the Authority in such form as the Authority may require.

Participants using solid biomass in accredited RHI installations with an installation capacity of 1MWth or aboveE+W+S

38.—(1) This regulation applies to a participant generating heat from solid biomass, not being solid biomass contained in waste, in an accredited RHI installation with an installation capacity of 1MWth or above.

(2) The participant may use solid biomass contaminated with fossil fuel only where the proportion of fossil fuel contamination does not exceed 10%.

(3) Such contaminated biomass may not be used unless the fossil fuel is present because—

(a)the solid biomass has been subject to a process, the undertaking of which has caused the fossil fuel to be present in, on or with the biomass even though that was not the object of the process; or

(b)the fossil fuel is waste and was not added to the solid biomass with a view to its being used as a fuel.

(4) For the purposes of paragraph (2)—

(a)the proportion of fossil fuel contamination is to be determined by the Authority for every quarterly period;

(b)it is for the participant to provide, in such form as the Authority may require, evidence to demonstrate to the Authority's satisfaction the proportion of fossil fuel contamination; and

(c)the proportion of fossil fuel contamination is the energy content of the fossil fuel with which the solid biomass used in any quarterly period is contaminated expressed as a percentage of the energy content of all solid biomass (contaminated or otherwise) used in that quarterly period to generate heat other than fossil fuel used in accordance with paragraphs (5) and (6).

(5) The participant may use fossil fuel (other than fossil fuel mentioned in paragraph (2)) in the accredited RHI installation for the following permitted ancillary purposes only—

(a)cleansing other fuels from the accredited RHI installation's combustion system prior to using fossil fuel to heat the combustion system to its normal temperature;

(b)the heating of the accredited RHI installation's combustion system to its normal operating temperature or the maintenance of that temperature;

(c)the ignition of fuels of low or variable calorific value;

(d)emission control;

(e)in relation to accredited RHI installations which are CHP systems, standby generation or the testing of standby generation capacity.

(6) The energy content of the fossil fuel used during a quarterly period for the permitted ancillary purposes specified in paragraph (5) must not exceed 10% of the energy content of all the fuel used by that accredited RHI installation or where the installation is a CHP system, by a combustion unit which supplies energy to that installation from solid biomass, to generate heat during that quarterly period.

(7) Without prejudice to paragraph (4)(b), in determining the proportion of solid biomass composed of fossil fuel the Authority may have regard to any information (whether or not produced to it by the participant) if, in its opinion, that information indicates what proportion of the contaminated solid biomass is composed of fossil fuel.

(8) Where the Authority so requests, the participant must arrange for samples of the fuel used (or to be used) in the accredited RHI installation, or of any gas or other substance produced as the result of the use of such fuel, to be taken by a person (and analysed in a manner) specified by the Authority, and for the results of that analysis to be made available to the Authority in such form as the Authority may require.

Participants using solid biomass in accredited RHI installations with an installation capacity of 45kWth and above but below 1MWthE+W+S

39.—(1) This regulation applies to a participant generating heat from solid biomass, not being solid biomass contained in waste, in an accredited RHI installation with an installation capacity of 45kWth and above but below 1MWth.

(2) The participant may use solid biomass contaminated with fossil fuel provided the participant complies with paragraphs (2), (3), (5) and (6) of regulation 38 as well as the requirements of this regulation.

(3) Where solid biomass contaminated with fossil fuel is used in an accredited RHI installation, the participant must keep and provide upon request written evidence including invoices, receipts and such other documentation as the Authority may specify relating to fuel use and fossil fuel used for the permitted ancillary purposes specified in regulation 38(5) and provide this information upon request to the Authority, in such form as the Authority may require, to demonstrate compliance with this regulation.

(4) Without prejudice to paragraph (3), the Authority may have regard to any information (whether or not produced to it by the participant) if, in its opinion, that information indicates what proportion of the contaminated solid biomass is composed of fossil fuel.

(5) Where—

(a)the Authority is not satisfied that the proportion of fossil fuel contamination (within the meaning of regulation 38(4)(c)) does not exceed 10%; or

(b)the Authority is not satisfied as to the matters specified in paragraphs (5) and (6) of regulation 38,

the Authority may require the participant to arrange for samples of the fuel used (or to be used) in the accredited RHI installation, or of any gas or other substance produced as the result of the use of such fuel, to be taken by a person (and analysed in a manner) specified by the Authority, and for the results of that analysis to be made available to the Authority in such form as the Authority may require.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources