77.—(1) A participant—
(a)who is a producer of biomethane for injection;
(b)whose original application for registration was made on or after 28th May 2014; and
(c)who is producing additional biomethane for injection,
may apply to the Authority to be registered in respect of that additional biomethane.
(2) Regulation 32(2) to (8), (10)(a) to (c) and (e), and (11) to (14) applies to an application for registration in respect of additional biomethane, but as if—
(a)references to an applicant were references to the participant,
(b)references to biomethane were references to additional biomethane,
(c)references to registering the applicant as a participant were references to registering the participant in respect of that additional biomethane.
(3) Where a participant is registered in respect of additional biomethane, the Authority must specify the maximum additional capacity in relation to which the participant is being registered.
(4) Periodic support payments for additional biomethane may not be made beyond the tariff end date notified in accordance with regulation 32(10)(d) when the participant was originally registered as a producer of biomethane for injection.
(5) For the purposes of this regulation—
(a)“additional biomethane” means any biomethane—
(i)which exceeds the sum of the maximum initial capacity, together with any maximum additional capacity previously specified under this regulation; and
(ii)which is being supplied by the participant for injection at the same injection point as the biomethane in respect of which that participant was first registered;
(b)“maximum additional capacity” means the volume of biomethane expressed in cubic metres per quarterly period which—
(i)is additional biomethane; and
(ii)is the maximum volume which a participant is entitled to supply for injection under the network entry agreement applicable to that additional biomethane.
(6) Where the Authority does not register an applicant in respect of additional biomethane, it must notify the applicant in writing that the application for registration has been rejected, giving reasons.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: