Articles 2(1) and 3

SCHEDULE 1SCHEDULED WORKS

In the County of Buckinghamshire, District of Aylesbury Vale

Parishes of Quainton and Grendon Underwoood

Work No. 1 – A railway siding (1090 metres in length) to serve the Calvert Landfill and the Greatmoor Energy from Waste Facility in the District of Aylesbury Vale, County of Buckinghamshire commencing by a junction with the Aylesbury Link at a point 330 metres south east of the bridge carrying bridleway QUA/36/2 over the Aylesbury Link and terminating by a junction with the Aylesbury Link at a point 166 metres north west of the bridge carrying bridleway GUN/28/1 over the Aylesbury Link.

Parishes of Grendon Underwood and Calvert Green

Work No. 2 – A railway siding (720 metres in length) for the loading and offloading of spoil and waste material to the Calvert Landfill and the Greatmoor Energy from Waste Facility in the District of Aylesbury Vale, County of Buckinghamshire commencing by a junction with Work No. 1 at a point 44 metres south east of the bridge carrying bridleway GUN/28/1 over the Aylesbury Link and terminating at a point 90 metres north of the junction of footpath CAG/2/1 with Bridleway CAG/3/1.

Work No. 3 - A railway siding (680 metres in length) for the loading and offloading of spoil and waste material to the Calvert Landfill and the Greatmoor Energy from Waste Facility in the District of Aylesbury Vale, County of Buckinghamshire commencing by a junction with Work No. 1 at a point 10 metres east of the bridge carrying bridleway GUN/28/1 over the Aylesbury Link and terminating at a point 66 metres north of the junction of footpath CAG/2/1 with Bridleway CAG/3/1.

Parish of Quainton

Work No. 4 - A bridge over Work No. 1 commencing on bridleway QUA/36/2 at a point 86 metres south-west of the bridge carrying that bridleway over the Aylesbury Link and terminating on bridleway QUA/36/3 at a point 96 metres north-east of that bridge.

Parishes of Quainton and Grendon Underwood

Work No. 5 – An access road commencing at a point 90 metres west of the bridge carrying bridleway QUA/36/2 over the Aylesbury Link and terminating at a point 194 metres south of the bridge carrying bridleway GUN/28/1 over the Aylesbury Link.

Parish of Grendon Underwood

Work No. 6 - A bridge over Work No. 1 commencing at a point 204 metres south of the bridge carrying bridleway GUN/28/1 over the Aylesbury Link and terminating at a point 108 metres north of that bridge.