PART 4MISCELLANEOUS AND GENERAL

Defence to proceedings in respect of statutory nuisance29.

(1)

Where proceedings are brought under section 82(1) (summary proceedings by person aggrieved by statutory nuisance) of the Environmental Protection Act 199046 in relation to a nuisance falling within paragraph (g) of section 79(1)47 of that Act (noise emitted from premises so as to be prejudicial to health or a nuisance) no order is to be made, and no fine may be imposed, under section 82(2) of that Act if—

(a)

the defendant shows that the nuisance—

(i)

relates to premises used by Network Rail for the purposes of or in connection with the exercise of the powers conferred by this Order with respect to the authorised works and that the nuisance is attributable to the carrying out of the authorised works in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site), of the Control of Pollution Act 197448; or

(ii)

is a consequence of the operation of the authorised works and that it cannot reasonably be avoided.

(2)

Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), do not apply where the consent relates to the use of premises by Network Rail for the purposes of or in connection with the exercise of the powers conferred by this Order with respect to works.