SCHEDULES

SCHEDULE 2REQUIREMENTS

Commissioning of authorised development: notice of commencement and completion

4.—(1) Notice of the commencement of commissioning must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.

(2) Notice of the completion of commissioning must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.