Certification of plans etc.E+W+S

39.—(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—

(a)the book of reference;

(b)design principles statement;

(c)the environmental statement, which includes within its appendices the following—

(i)outline construction environment management plan;

(ii)outline landscape and ecological mitigation strategy;

(iii)outline surface water management plan;

(iv)flood consequences assessment;

(v)outline drainage strategy;

(vi)outline construction traffic management plan;

(vii)outline construction staff travel plan;

(viii)outline lighting strategy;

(d)the land plans;

(e)the rights of way, streets and access plan; and

(f)the works plans; and

(g)hedgerow plan,

for certification that they are true copies of the documents referred to in this Order.

(2) A plan or document so certified is to be admissible in any proceedings as evidence of the contents of the document of which it is a copy.