SCHEDULE 12E+W+SPROCEDURE FOR DISCHARGE OF REQUIREMENTS

Applications made under requirementsE+W+S

1.—(1) Where an application has been made to the relevant planning authority for any consent, agreement or approval required by a requirement (including agreement or approval in respect of part of a requirement) included in this Order the relevant planning authority must give notice to the undertaker of their decision on the application within a period of eight weeks beginning with—

(a)the day immediately following that on which the application is received by the authority;

(b)the day immediately following that on which further information has been supplied by the undertaker under paragraph 2; or

such longer period as may be agreed in writing by the undertaker and the relevant planning authority.

(2) Subject to sub-paragraph (3), in the event that the relevant planning authority does not determine an application within the period set out in sub-paragraph (1), the relevant planning authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.

(3) Any application made to the relevant planning authority pursuant to sub-paragraph (1) must include a statement to confirm whether it is likely that the subject matter of the application will give rise to any materially new or materially different environmental effects compared to those in the environment statement and if it will then it must be accompanied by information setting out what those effects are.

(4) Where an application has been made to the relevant planning authority for any consent, agreement or approval required by a requirement included in this Order and the relevant planning authority does not determine the application within the period set out in sub-paragraph (1), then if either—

(a)the application is accompanied by a report pursuant to sub-paragraph (3) which states that the subject matter of such application is likely to give rise to any materially new or materially different environmental effects compared to those in the environmental statement; or

(b)the relevant planning authority determines during the period set out in sub-paragraph (1) that it considers that the subject matter of such application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement,

then the application is to be taken to have been refused by the relevant planning authority at the end of that period.

(5) Where an application is made to a relevant planning authority for a consent, agreement or approval required by a requirement they may grant such consent, agreement or approval either unconditionally or subject to conditions.

Commencement Information

I1Sch. 12 para. 1 in force at 10.10.2019, see art. 1