There are currently no known outstanding effects for the The Drax Power (Generating Stations) Order 2019, PART 2 .
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
3.—(1) Subject to the provisions of this Order and to the Requirements, the undertaker is granted development consent for the authorised development to be carried out within the Order limits.
(2) Each numbered work maybe situated only within the corresponding numbered area shown on the works plans and within the limits of deviation.
Commencement Information
I1Art. 3 in force at 25.10.2019, see art. 1
4.—(1) The undertaker may at any time maintain the authorised development except to the extent that this Order or an agreement made under this Order provides otherwise.
(2) This article authorises the carrying out of maintenance works only within the Order limits.
Commencement Information
I2Art. 4 in force at 25.10.2019, see art. 1
5.—(1) The undertaker is authorised to use and operate the generating stations comprised in the authorised development.
(2) This article does not relieve the undertaker of any other requirement to obtain any permit or licence or any obligation under any legislation that may be required to authorise the operation of a generating station.
Commencement Information
I3Art. 5 in force at 25.10.2019, see art. 1
6. Subject to article 7 (consent to transfer F1... benefit of the Order), the provisions of this Order have effect solely for the benefit of Drax Power Limited save for—
(a)Work No. 6A in relation to which the provisions of this Order have effect for the benefit of Drax Power Limited and NGG; and
(b)Work No 8 in relation to which the provisions of this Order have effect for the benefit of Drax Power Limited and NGET.
Textual Amendments
F1Word in art. 6 omitted (19.8.2020) by virtue of The Drax Power (Generating Stations) (Correction) Order 2020 (S.I. 2020/879), art. 1(2), Sch.
Commencement Information
I4Art. 6 in force at 25.10.2019, see art. 1
7.—(1) Subject to paragraph (4), the undertaker may—
(a)transfer to another person (“the transferee”) any or all of the benefit of the provisions of this Order which resides for the time being in the undertaker (including any of the numbered works) and such related statutory rights as may be agreed in writing between the undertaker and the transferee; or
(b)grant to another person (“the lessee”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order which resides for the time being in the undertaker (including any of the numbered works) and such related statutory rights as may be so agreed.
(2) Where a transfer or grant has been made in accordance with paragraph (1) references in this Order to the undertaker, except in paragraph (3), include references to the transferee or the lessee.
(3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or grant under paragraph (1) is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.
(4) The consent of the Secretary of State is required for the exercise of the powers of paragraph (1) except where—
(a)the transferee or lessee is—
(i)the holder of a licence under section 6 of the Electricity Act 1989 M1;
(ii)in relation only to a transfer or lease of Work No. 6 or Work No. 7, the holder of a licence under section 7 of the Gas Act 1986 M2; or
(iii)in relation to a transfer or lease of any works within a highway, a highway authority responsible for the highways within the Order land; or
(b)the time limits for all claims for compensation in respect of the acquisition of land or effects upon land under this Order have elapsed and—
(i)no such claims have been made;
(ii)any such claims that have been made have all been compromised or withdrawn;
(iii)compensation has been paid in final settlement of all such claims;
(iv)payment of compensation into court in lieu of settlement of all such claims has taken place; or
(v)it has been determined by a tribunal or court of competent jurisdiction in respect of all such claims that no compensation is payable.
(5) Where the consent of the Secretary of State is not required under paragraph (4), the undertaker must notify the Secretary of State in writing before transferring or granting a benefit referred to in paragraph (1).
(6) The notification referred to in paragraph (5) must state—
(a)the name and contact details of the person to whom the benefit of the powers will be transferred or granted;
(b)subject to paragraph (7), the date on which the transfer will take effect;
(c)the powers to be transferred or granted;
(d)pursuant to paragraph (3), the restrictions, liabilities and obligations that will apply to the person exercising the powers transferred or granted; and
(e)where relevant, a plan showing the works or areas to which the transfer or grant relates.
(7) The date specified under paragraph (6)(b) must not be earlier than the expiry of five working days from the date of the receipt of the notice.
(8) The notice given under paragraph (6) must be signed by the undertaker and the person to whom the benefit of the powers will be transferred or granted as specified in that notice.
8.—(1) The provisions of the Neighbourhood Planning Act 2017 M3 insofar as they relate to temporary possession of land under articles 28 (temporary use of land for carrying out the authorised development) and 29 (temporary use of land for maintaining the authorised development) do not apply in relation to the construction of any work or the carrying out of any operation required for the purpose of, or in connection with, the construction, operation or maintenance of any part of the authorised development.
(2) As from the date on which the authorised development (including the permitted preliminary works) is commenced any approval, grant, permission, authorisation or agreement made under the Planning Acts or Electricity Acts prior to that date will cease to have effect but only insofar as such approval, grant, permission, authorisation or agreement is inconsistent with the authorised development or anything approved under the Requirements to be carried out within the Order limits.
(3) The following provisions do not apply in relation to the construction of any work or the carrying out of any operation required for the purpose of, or in connection with, the construction, operation or maintenance of the authorised development—
(a)section 23 (prohibition of obstructions, etc. in watercourses) of the Land Drainage Act 1991 M4; and
(b)any byelaws made under section 66 (powers to make byelaws) of the Land Drainage Act 1991.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: