The Electricity and Gas etc. (Amendment etc.) (EU Exit) Regulations 2019

This section has no associated Explanatory Memorandum

34.—(1) Section 34 (general functions of the Gas and Electricity Markets Authority) is amended as follows.

(2) In subsection (2A)—

(a)in paragraph (b), for “and (r) to” substitute “ , (r) and ”;

(b)omit paragraph (d) (but not the “and” following it).

(3) After subsection (2A) insert—

(2B) For the purposes of subsection (2A)(c), the reference to Article 41(3)(a) is to be read as if the reference in that provision to Article 41 were a reference to Article 41 as implemented in Great Britain immediately before [F1IP completion day]..

Textual Amendments

Commencement Information

I1Reg. 34 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1(1)