
Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThis
Section
only
Changes over time for: Section 40


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 03/04/2019.
Changes to legislation:
There are currently no known outstanding effects for the The Millbrook Gas Fired Generating Station Order 2019, Section 40.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Procedure in relation to certain approvalsE+W+S
40.—(1) Where an application is made to or a request is made of the relevant planning authorities, highway authority, traffic authority, street authority, or the owner of a watercourse, sewer or drain or the beneficiary of any of the protective provisions contained in Schedule 10 (protective provisions) for any consent, agreement or approval required or contemplated by any of the provisions of the Order (not including the requirements but including the protective provisions contained in Schedule 10), such consent, agreement or approval to be validly given, must be given in writing and must not be unreasonably withheld or delayed.
(2) Schedule 12 (procedure for discharge of requirements) has effect in relation to all consents, agreements or approvals granted, refused or withheld in relation to the requirements in Schedule 2 (requirements).
(3) Save for applications made pursuant to Schedule 12 (procedure for discharge of requirements) and where stated to the contrary if, within eight weeks after the application or request has been submitted to an authority, beneficiary of protective provisions or an owner as referred to in paragraph (1) of this article (or such longer period as may be agreed with the undertaker in writing) it has not notified the undertaker of its disapproval and the grounds of disapproval, it is deemed to have approved the application or request.
(4) The procedure set out in paragraph 1(3) of Schedule 12 (procedure for discharge of requirements) has effect in relation to any refusal by an authority, beneficiary of protective provisions, or an owner as referred to in paragraph (1) of this article to any consent, agreement or approval required under this Order, including such as may be required pursuant to the protective provisions contained within Schedule 10 (protective provisions).
(5) Where any application is made as described in paragraph (1), the undertaker must include a statement in such application that refers to the timeframe for consideration of the application and the consequences of failure to meet that timeframe as prescribed by paragraph (3).
Back to top