The Millbrook Gas Fired Generating Station Order 2019

Changes over time for: SCHEDULE 1

 Help about opening options

Alternative versions:

Status:

Point in time view as at 09/04/2020.

Changes to legislation:

There are currently no known outstanding effects for the The Millbrook Gas Fired Generating Station Order 2019, SCHEDULE 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 3

SCHEDULE 1E+W+SAUTHORISED DEVELOPMENT

Commencement Information

I1Sch. 1 in force at 3.4.2019, see art. 1

In Central Bedfordshire—

A nationally significant infrastructure project as defined in sections 14(1)(a) and 15 of the 2008 Act, and associated development under section 115(1)(b) of that Act consisting of a generating station with a gross rated electrical output of up to 299MWe comprising all or part of—

Work No. 1A development comprising a generating station including—

(a)1 gas turbine generator;

(b)1 exhaust gas emission flue stack; and

(c)external fin fan cooler(s),

Work No. 1B development comprising a generating station and gas and electrical infrastructure including—

(a)a control room/office/workshop;

(b)telemetry apparatus;

(c)a fire water tank;

(d)a demineralised water storage tank;

(e)an emergency generator including fuel storage tank;

(f)gas pipeline and telemetry cabling and cathodic protection test/ transformer rectifier unit;

(g)a natural gas receiving station and gas treatment compound containing—

(i)a pipeline inspection gauge (PIG) receiving facility;

(ii)isolation valves, metering, heating, filtering, compression, pressure regulation equipment;

(iii)electricity supply kiosks;

(iv)emergency generator including fuel storage tank;

(v)Joule-Thomson boiler(s); and

(vi)control and instrumentation kiosks,

Work No. 1C development comprising a generating station and electrical infrastructure including a transformer compound, generator step up transformer, unit and other transformers, F1... overhead conductors and other plant and structures required to manage the transmission of electricity,

Textual Amendments

Work No. 1D development comprising a generating station including—

(a)security infrastructure, including cameras, perimeter fencing and a gatehouse;

(b)site lighting infrastructure, including perimeter lighting columns;

(c)internal roadways, car parking, pedestrian network, cycle parking, hardstanding and water treatment trailers;

(d)a maintenance compound including hardstanding and welfare and administration facilities;

(e)site drainage and waste management infrastructure, including relocation of existing infrastructure as required;

(f)electricity, water, wastewater and telecommunications and other services including high voltage and low voltage cabling, equipment and controls and associated telemetry and electrical protection auxiliary cabling;

(g)landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation; and

(h)other ancillary equipment.

Work No. 2A development comprising the creation of a junction with Green Lane, maintenance of an existing access road between Green Lane and Rookery South Pit, including permanent road surface and kerb stones, fencing, safety barrier(s), signing and road markings works, footway, drainage (including culverts), electricity and telecommunications connections and other services and other incidental works,

Work No. 2B development comprising a new means of access, including permanent road surface and kerb stones, safety barrier(s), signing and road markings works, footway, drainage (including culverts), electricity and telecommunications connections and other services and other incidental works,

Work No. 3A development comprising gas infrastructure including—

(a)an above ground installation (also referred to as a minimum offtake connection compound) containing—

(i)a minimum offtake connection comprising remotely operable valves, control and instrumentation kiosks and electrical supply kiosks;

(ii)a pipeline inspection gauge (PIG) facility, comprising a PIG launching facility, emergency control valves, isolation valves, control and instrumentation kiosks, and electricity supply kiosks;

(b)security infrastructure, including cameras, lighting (including perimeter lighting columns) and perimeter fencing;

(c)site drainage and waste management infrastructure;

(d)electricity and telecommunications connections and other services;

(e)below ground sacrificial anode pit; and

(f)landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation,

Work No. 3B development comprising creation of a permanent access and a construction access from an existing agricultural track into numbered work 3A, upgrading of an existing agricultural track and junction between Houghton Lane and numbered work 3A, including permanent road surface and kerb stones, signing and road markings works, drainage (including culverts), electricity and telecommunications connections and other services and other incidental works,

Work No. 4A development comprising a gas pipeline including—

(a)a new underground gas pipeline connection and telemetry cabling, approximately 1.8km in length connecting Work No. 1B to Work No. 3A;

(b)pipeline field marker posts and cathodic protection test/ transformer rectifier unit;

(c)below ground drainage works;

(d)works required in order to protect existing utilities infrastructure;

(e)tree and hedge removal;

(f)landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation; and

(g)creation of construction access from Houghton Lane,

Work No. 4B development comprising a construction laydown area including areas of hardstanding and site and welfare offices and workshop;

Work No. 5 [F2development comprising electrical infrastructure between Work No. 1 and Work No. 6 including—

(a)underground high voltage electrical cables and associated telemetry and electrical protection auxiliary cabling;

(b) landscaping including tree planting, temporary fencing and other boundary treatments and ecological mitigation; and

(c)site drainage,]

Textual Amendments

Work No. 6 [F3development comprising an electrical substation at transmission tower ZA378 and works to construct a 400kV electrical connection between transmission tower ZA378 and Work No. 5 and mitigation works for Works Nos. 1, 3, 6, and 7—

(a)400kV electricity substation including site office and welfare accommodation, emergency auxiliary supplies and downleads to connect to existing tower ZA378;

(b)underground or ducted high voltage electrical cables and associated telemetry and electrical protection auxiliary cabling and below ground drainage works;

(c)security infrastructure including perimeter fencing with gates, security cameras, site lighting infrastructure, including perimeter lighting columns;

(d)permanent means of access from the low level restoration scheme secondary access to numbered work 6(a), taking the form of an agricultural hard-core track not more than 6 m wide and creation of permanent diversion of the low level restoration scheme secondary access;

(e)permanent means of access taking the form of an agricultural hard-core track not more than 6 m wide;

(f)landscaping including bunds, tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation;

(g)site drainage and waste management infrastructure, including the diversion of a watercourse;

(h)electricity and telecommunications connections and other services;

(i)internal roadways, car parking, pedestrian network and hardstanding for planning maintenance; and

(j) construction laydown area(s) including areas of hardstanding and site and welfare offices and workshops,]

Textual Amendments

Work No 7 [F4development comprising works to transmission towers and mitigation works for Works Nos. 1, 3, 6 and 7 including—

(a) alterations of cross-arms on tower ZA378 to accommodate downleads to new substation;

(b) erection and later removal of scaffolding, re-stringing of conductors in the alignment of the existing 400kV transmission line;

(c)tree, hedge and fence removal;

(d)security infrastructure including temporary perimeter fencing with gates, security cameras and site lighting; and

(e)landscaping including tree planting, fencing and ecological mitigation,]

Textual Amendments

Work No. 8 development comprising a construction laydown area(s) including areas of hardstanding and site and welfare offices and workshops,

and such other buildings, structures, works or operations as may be necessary or expedient for the purposes of or in connection with the construction, operation and maintenance of the works in this Schedule but only within the Order limits and insofar as they are unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources