SCHEDULE 1AUTHORISED DEVELOPMENT
Work No. 5 development comprising an electrical substation and electrical infrastructure including—
(a)
400kV substation including overhead line gantry and site office and welfare accommodation and emergency auxiliary supplies;
(b)
underground high voltage electrical cables and associated telemetry and electrical protection auxiliary cabling;
(c)
security infrastructure including perimeter fencing with gates, security cameras and site lighting infrastructure, including perimeter lighting columns;
(d)
landscaping including bunds, tree planting, fencing and other boundary treatments and ecological mitigation;
(e)
site drainage and waste management infrastructure;
(f)
electricity and telecommunications connections and other services; and
(g)
internal roadways, car parking, pedestrian network and hardstanding for planned maintenance,