SCHEDULE 5

I11

The following table applies for the purpose of setting the outline planning zone under regulation 9(1)(a).

Category

Nature of site

Outline planning zone

1

Sites involved in the processing of High Level Waste or storing in excess of 100 tonnes of Plutonium

50 kilometres

2

Operating nuclear power plants and decommissioning nuclear power plants with a presence of irradiated fuels

30 kilometres

3

Sites with a significant presence of enriched uranium and decommissioning nuclear sites (other than power plants) with a significant presence of irradiated fuels

5 kilometres

4

Decommissioned sites without a significant presence of irradiated fuels

1 kilometre

5

Sites involved in the production of radiopharmaceuticals

No outline planning zone