14.—(1) No phase of the authorised development may commence other than preliminary works until the relevant planning authority has received and approved in writing a waste management plan relating to the construction of that phase of the authorised development.
(2) The plan must incorporate the principles in and be based on the draft waste management plan contained in Annex D4 of the environmental statement and must address and include at least the following—
(a)the storage of waste materials on site;
(b)removal of waste materials from the site for recovery or disposal at appropriately licensed sites;
(c)a materials management plan;
(d)a sediment control plan; and
(e)monitoring measures.
(3) The approved waste management plan must be implemented as approved and maintained during construction of that phase of the authorised development.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: