CHAPTER 1Supplier charge payments during standstill period

Settlement Body to hold supplier charge payments

7.—(1) The Settlement Body must hold any capacity market supplier charge and any other payments it receives from electricity suppliers under regulation 6A(7) of the Supplier Payment Regulations(1) (unless returned to the electricity supplier which made the payment) to enable it to meet the cost of making capacity payments—

(a)in respect of capacity obligations contained in capacity agreements that existed on 15th November 2018 which were payable in respect of a standstill month (but were prevented by the law relating to state aid from being paid at the time); and

(b)in respect of capacity obligations awarded through the conditional agreement auction in respect of a T-1 standstill month.

(2) In this regulation, “T-1 standstill month” means—

(a)any month included (wholly or partly) in the T-1 standstill period; or

(b)the month after the month in which the T-1 capacity agreement trigger event or T-1 termination trigger event occurs.

(3) For the purposes of paragraph (2), “T-1 standstill period” means any part of the delivery year beginning on 1st October 2019 which falls before the date on which the T-1 capacity agreement trigger event or T-1 termination trigger event occurs.

Supplier charge payments used to make capacity payments: deferred capacity payment trigger event

8.  If the deferred capacity payment trigger event occurs, the Settlement Body must use the capacity market supplier charge and any other payments it holds under regulation 7(1) on the day on which the trigger event occurs to meet the cost of making the capacity payments described in regulation 7(1)(a) in accordance with regulation 40 of the Principal Regulations(2).

Supplier charge payments used to make capacity payments: T-1 capacity agreement trigger event

9.  If the T-1 capacity agreement trigger event occurs, the Settlement Body must use the supplier charge and any other payments it holds under regulation 7(1) on the day on which the trigger event occurs to meet the cost of making capacity payments to capacity providers in respect of capacity obligations awarded through the conditional agreement auction in accordance with regulations 40 and 40A of the Principal Regulations(3).

Return of supplier charge payments: agreement termination trigger event

10.—(1) If the agreement termination trigger event and T-1 termination trigger event have both occurred, the Settlement Body must, for each electricity supplier (“S”), as soon as reasonably practicable after both trigger events have occurred—

(a)determine the amount of supplier charge and any other payments paid by S which it holds under regulation 7(1) on the day on which the trigger event occurs;

(b)determine the amount of interest payable (if any) on the amount determined under sub-paragraph (a); and

(c)make a payment to S for an amount determined by adding the amounts determined under sub-paragraphs (a) and (b).

(2) In paragraph (1)(b), interest is payable only if there is a legal obligation to pay S interest in respect of the amount determined under paragraph (1)(a), and is only payable to the extent of that legal obligation.

(1)

Regulation 6A(7) is read into those regulations as modifications to the application of the Supplier Payment Regulations made by regulation 56(2).

(2)

Regulation 40 applies in respect of those payments as modified by regulation 13.

(3)

Regulations 40 and 40A apply in respect of those payments as modified by regulation 38.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources