EXPLANATORY NOTE

(This note is not part of the Order)

This Order confers further powers of compulsory acquisition on the West Midlands Combined Authority (“the Executive”) for the purpose of the works authorised by the Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (“the 2005 Order”). Powers for compulsory acquisition under the 2005 Order expired on 22nd July 2010.

A copy of the land plans and the book of reference referred to in this Order may be inspected at the offices of the Executive at 16 Summer Lane, Birmingham, B19 3SD.