The Electricity and Gas (Internal Markets and Network Codes) (Amendment etc.) (EU Exit) Regulations 2020

This section has no associated Explanatory Memorandum

11.—(1) Article 11 (value of lost load) is amended as follows.

(2) For paragraph 1 substitute—

1.  Where required for the purpose of setting a reliability standard in accordance with Article 25, the relevant authority must determine a single estimate of the value of lost load for Great Britain. That estimate must be made publicly available. The relevant authority may determine different estimates per bidding zone if there is more than one bidding zone in Great Britain. Where a bidding zone consists of more than one control area, the relevant authority must determine a single estimate of the value of lost load for that bidding zone..

(3) In paragraph 2—

(a)for “Regulatory authorities and designated competent authorities” substitute “The relevant authority”;

(b)for “their” substitute “its”;

(c)for “they” substitute “it”;

(d)for “observe” substitute “observes”.

(4) After paragraph 2, insert—

3.  In this Article, “relevant authority” means the Secretary of State or the regulatory authority..