SCHEDULE 3E+W+SLAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

This schedule has no associated Explanatory Memorandum

Commencement Information

I1Sch. 3 in force at 23.9.2020, see Order

(1)Area(2)Number of land shown on the deposited plans(3)Purpose for which temporary possession may be taken
Metropolitan Borough of Sandwell9, 16 and 19Construction access and working space; works for retention of flood storage during construction
22, 23, 24, 25 and 27Construction access and working space, temporary diversion of public footpath and possible right of way on foot
36, F1... 40, 41, 43, 44 to 51, 60, 73, 75, 76, 78, 79, [F284 to 86, 88,] 94, 101, 102, 106, 120, 122 to 125, 129, 135, 136, 138 and 139Working site, construction access and working space
137Construction access and works including works to existing footpath
Metropolitan Borough of Dudley149, 170, 173, 175, 182, 197, 199, 200, 254c, 256, 258, 268 to 271, 274, 276, 278, 280, 281, 292, 295, 296, F3... 316, 329, 338 and 347Working site, construction access and working space
165 and 169Landscaping
167, 168, 170, 172 and 174Remodelling of bus station
312 and 317Construction access and safeguarding works to existing railway