The Great Yarmouth Third River Crossing Development Consent Order 2020

ArbitrationE+W+S

67.—(1) Except where otherwise expressly provided for in this Order and unless otherwise agreed between the parties, any difference under any provision of this Order (other than a difference which falls to be determined by the tribunal) must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.

(2) Paragraph (1) does not apply to any decision, difference, determination, approval or permission required by or under any provision of the deemed marine licence in Schedule 13.

Commencement Information

I1Art. 67 in force at 15.10.2020, see art. 1