SCHEDULES

SCHEDULE 13E+W+SDEEMED MARINE LICENCE

PART 2 E+W+SCONDITIONS

Construction method statementE+W+S

5.—(1) The licence holder must submit a construction method statement, for approval by the MMO, at least 13 weeks prior to the commencement of any construction activity.

(2) The construction method statement must include the following details—

(a)the detailed construction methodology to be employed by the licence holder in carrying out the construction activity; and

(b)a programme of works including timings and durations, method of delivery of material to site and plant to be used during the works.

(3) The licence holder must not commence the construction activity until the MMO has approved in writing the submitted construction method statement.

(4) The construction activity must be carried out in accordance with the approved construction method statement, unless otherwise agreed in writing by the MMO.

Commencement Information

I1Sch. 13 para. 5 in force at 15.10.2020, see art. 1