The Great Yarmouth Third River Crossing Development Consent Order 2020

Noise registry

6.  Where impact piling is required as part of a construction method statement approved by the MMO under condition 5, the licence holder must—

(a)prior to the commencement of a licensed activity in the river Yare which involves impact pile driving—

(i)submit details of the expected location, start and end dates of impact pile driving to the Marine Noise Registry in order to satisfy the forward look requirements of the Marine Noise Registry; and

(ii)send copies of the notifications required under sub-paragraph (i) to the MMO Marine Licensing Team within 5 days of the date of submission of the details required under sub-paragraph (i); and

(b)within 12 weeks of completion of a licensed activity in the river Yare which involves impact pile driving—

(i)submit details of the actual location, start and end dates of impact pile driving to the Marine Noise Registry in order to satisfy the close out requirements of the Marine Noise Registry; and

(ii)send copies of the notifications required under sub-paragraph (i) within 5 days of the date of submission of the details required under sub-paragraph (i).