SCHEDULES

SCHEDULE 14E+W+SPROTECTIVE PROVISIONS

PART 4 E+W+SFOR THE PROTECTION OF THE ENVIRONMENT AGENCY

34.  If by reason of construction of the specified work the Agency's access to flood defences or equipment maintained for flood defence purposes is materially obstructed, the undertaker must provide such alternative means of access that will allow the Agency to maintain the flood defence or use the equipment no less effectively than was possible before the obstruction within 48 hours of the undertaker becoming aware of such obstruction.E+W+S

Commencement Information

I1Sch. 14 para. 34 in force at 15.10.2020, see art. 1