The Great Yarmouth Third River Crossing Development Consent Order 2020

58.  Any specified work must, when commenced be constructed—E+W+S

(a)without unnecessary delay;

(b)in such a manner as to cause as little adverse effects as is reasonably practicable to the river;

(c)in such a manner as to cause no material adverse effects to the integrity of the walls or banks of the river; and

(d)in such a manner as to cause as little inconvenience as is reasonably practicable to the GYPA.

Commencement Information

I1Sch. 14 para. 58 in force at 15.10.2020, see art. 1