SCHEDULES
SCHEDULE 14PROTECTIVE PROVISIONS
PART 6FOR THE PROTECTION OF THE GREAT YARMOUTH PORT AUTHORITY
68.
Within 3 months of completion of the specified works and protective works (“the completed works”), the undertaker must provide to the GYPA drawings of the completed works as constructed, including the electrical and mechanical drawings of the opening and closing mechanisms of the new bridge. If any modifications are made to the completed works following their completion the undertaker must provide updated as built drawings of the modified works.