In this Schedule the following expressions have the following meanings—

the archaeological written scheme of investigation” means the document of that description referenced in Schedule 15 (documents to be certified) certified by the Secretary of State as the archaeological written scheme of investigation for the purposes of this Order;

the code of construction practice” means a code of construction practice approved under paragraph 73 of this Schedule;

the county planning authority” means Norfolk County Council in its capacity as county planning authority for the county of Norfolk under section 1(1)(a) (local planning authorities: general) of the 1990 Act;

the drainage strategy” means the document of that description referenced in Schedule 15 (documents to be certified) certified by the Secretary of State as the drainage strategy for the purposes of this Order;

the IDB” means the Waveney, Lower Yare and Lothingland Internal Drainage Board;

the lead local flood authority” means Norfolk County Council in its capacity as lead local flood authority under section 6(7) (other definitions) of the Flood and Water Management Act 2010 M1;

the outline code of construction practice” means the document of that description referenced in Schedule 15 (documents to be certified) certified by the Secretary of State as the outline code of construction practice for the purposes of this Order;

the landscaping plans” means the plans of that description referenced in Schedule 15 (documents to be certified) certified by the Secretary of State as the landscaping plans for the purposes of this Order;

the lighting report” means the document of that description referenced in Schedule 15 (documents to be certified) certified by the Secretary of State as the lighting report for the purposes of this Order; and

the preliminary navigation risk assessment” means the document of that description referenced in Schedule 15 (documents to be certified) certified by the Secretary of State as the preliminary navigation risk assessment for the purposes of this Order.