SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Lighting
12.
(1)
No part of the authorised development is to commence until a written scheme of the lighting to be provided for that part on opening for public use (except lighting to be provided to the interior of a building) has been submitted to and, following consultation with Great Yarmouth Borough Council, approved in writing by the county planning authority.
(2)
Any written scheme of proposed lighting submitted for approval under sub-paragraph (1) must be in accordance with the lighting report and include a timetable for implementation.
(3)
The part of the authorised development in question must be carried out in accordance with the scheme approved under sub-paragraph (1) for that part and the approved lighting must be maintained thereafter.
(4)
Nothing in this requirement restricts lighting of the authorised development during its construction or as temporarily required for maintenance.