Completion and availability of particular works
13.
(1)
The highway comprised in the new bridge and the new bridge western approach must not be opened for public use until the works specified in sub-paragraph (2) have been completed and made available for use.
(2)
The works are—
(a)
the vessel waiting facilities;
(b)
Work No. 11; and
(c)
Work No. 12.