5. Construction of each part of the authorised development specified in column (1) of the table below must not commence until the details of the elements specified in relation to that part in column (2) of that table have been submitted to, and following consultation with Great Yarmouth Borough Council, approved in writing by the county planning authority.
(1) Part of the authorised development | (2) Elements to be approved |
---|---|
Work No. 7A(i) | The external appearance of the control tower |
Work No.7B(i) | The external appearance of the plant room |
Work No.8A(iv) | The finish and external materials of the bridge deck |
Work No. 8B(i) | The finish and external materials of the bridge deck |
Work No. 8C(iv) | The finish and external materials of the bridge deck |
Commencement Information
I1Sch. 2 para. 5 in force at 15.10.2020, see art. 1