SCHEDULES

SCHEDULE 2REQUIREMENTS

Interpretation1

1

In this Schedule—

  • “commercial use” means that the commissioning of the authorised development has been completed and it is generating electricity on a commercial basis;

  • “commissioning” means the process of assuring that all systems and components of the authorised development (which are installed or where installation is near to completion) are tested to verify that they function and are operable in accordance with the design objectives, specifications and operational requirements of the undertaker;

  • “local residents” means the residents living within the administrative areas of Nottinghamshire and Lincolnshire;

  • “local organisations” means organisations based or with their main activities within the administrative areas of Nottinghamshire and Lincolnshire;

  • “m” means metres;

  • “mAGL” means metres above ground level;

  • “mAOD” means metres above ordnance datum; and

  • “stage” of the authorised development means any part or parts of Works Nos. 1 to 10.

2

Where any requirement requires the authorised development to be carried out in accordance with matters including a plan, document, or details approved by the relevant planning authority, those matters are to be taken to include any amendments that may subsequently be approved in writing by the relevant planning authority.

3

Where an approval or agreement is required under the terms of a requirement or a document referred to in a requirement, or any requirement specifies “unless otherwise approved” or “unless otherwise agreed” by the relevant planning authority, such approval or agreement may only be given in relation to non-material changes where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval or agreement sought is unlikely to give rise to any greater environmental effects from those assessed in the environmental statement.