60.—(1) Where—
(a)an installation’s reportable emissions in a scheme year (the “excess year”) for which the installation is an ultra-small emitter exceed the maximum amount; and
(b)the operator of the installation fails to give notice to the regulator under paragraph 6 of Schedule 8 on or before 31st March in the following year (the “default year”) or at all,
the operator is liable to a civil penalty.
(2) The civil penalty is the sum of—
(a)£2,500; and
(b)CA + (RE x CP) for each scheme year (or part of a scheme year) falling within the penalty period (if any), where—
CA is an estimate of the costs avoided by the operator in the scheme year (or part of the scheme year) as a result of carrying out a regulated activity without the authorisation of the relevant permit;
RE is an estimate of the installation’s reportable emissions in the scheme year (or part of the scheme year) during which a regulated activity that was not authorised by a permit was carried out;
CP is the carbon price for the scheme year.
(3) The penalty period is the period—
(a)beginning on 1st January in the year following the default year; and
(b)ending on the earlier of the following—
(i)the day before the day on which a permit for the installation comes into force; and
(ii)the last day of the same allocation period as the excess year is in.
(4) But there is no penalty period if—
(a)1st January in the year following the default year is not in the same allocation period as the excess year; or
(b)a permit for the installation is in force on that date.
(5) When setting the amount of the civil penalty to be imposed, the regulator may increase the amount calculated under paragraph (2)(b) by a factor designed to ensure that the amount of the civil penalty exceeds the value of any economic benefit that the operator has obtained as a result of carrying out a regulated activity that was not authorised by the relevant permit.
(6) The regulator must—
(a)estimate CA and RE under paragraph (2); and
(b)exercise the regulator’s functions under paragraph (5),
in accordance with a direction given by the relevant national authority under section 52 of CCA 2008.
(7) In this article—
“maximum amount” has the meaning given in paragraph 1 of Schedule 8;
“relevant permit” means—
where a hospital or small emitter permit for the installation comes into force before the last day of the same allocation period as the excess year is in, a hospital or small emitter permit;
in any other case, a greenhouse gas emissions permit.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: