xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

Article 77

SCHEDULE 11U.K.Transitional provisions: installations

Permits under GGETSR 2012U.K.

1.—(1) This paragraph applies to a permit within the meaning of GGETSR 2012 that immediately before this Schedule comes into force authorises a regulated activity to be carried out at an installation.

(2) But this paragraph does not apply to a permit—

(a)in respect of which an application under regulation 13 of GGETSR 2012 for the surrender of the permit has been made but has yet to be determined;

(b)that is due, in accordance with provision made under GGETSR 2012, to be surrendered or revoked; or

(c)that authorises a regulated activity to be carried out at an installation included in the ultra-small emitter list for 2021-2025.

(3) Where the installation is included in the hospital and small emitter list for 2021-2025, the regulator must—

(a)convert the permit into a hospital or small emitter permit the provisions of which satisfy the requirements of paragraph 11 of Schedule 7 and that authorises the regulated activity to be carried out at the installation from 1st January 2021; and

(b)give notice of the conversion to the operator of the installation.

(4) In any other case, the regulator must—

(a)convert the permit into a greenhouse gas emissions permit the provisions of which satisfy the requirements of paragraph 4 of Schedule 6 and that authorises the regulated activity to be carried out at the installation from 1st January 2021; and

(b)give notice of the conversion to the operator of the installation.

(5) When converting a permit under sub-paragraph (3) or (4), the regulator may make only such changes to the operator's obligations under the permit as the regulator considers necessary to convert the permit into a greenhouse gas emissions permit or, as the case may be, a hospital or small emitter permit.

(6) But sub-paragraph (5) does not prevent the regulator correcting errors.

(7) When converting a permit under sub-paragraph (4), the regulator may include under paragraph 4(2)(d) of Schedule 6 a condition to give proper effect to Article 69(4) of the Monitoring and Reporting Regulation 2018 that requires the operator to submit a report to the regulator relating to non-conformities or recommendations for improvements stated in a verification report under [F1Commission Implementing Regulation (EU) 2018/2067 (as it had effect in EU law)] in respect of the scheme year (within the meaning of GGETSR 2012) beginning on 1st January 2020.

(8) The conversion of a permit under sub-paragraph (3) or (4) does not affect the operator's obligations under the permit in respect of specified emissions before 1st January 2021 (and GGETSR 2012 continue to apply in relation to such obligations).

(9) A permit that is converted under this paragraph continues in force as if issued under this Order until cancelled, surrendered or revoked under this Order.

Textual Amendments

Commencement Information

I1Sch. 11 para. 1 in force at 12.11.2020, see art. 2(1)

Applications for permits, etc. under GGETSR 2012U.K.

2.—(1) An application under regulation 10 of GGETSR 2012 for a permit for an installation that is made to the regulator before 1st January 2021, but not determined before that date—

(a)where the installation is included in the hospital and small emitter list for 2021-2025, must be treated as an application for a hospital or small emitter permit under paragraph 7 of Schedule 7 to this Order;

(b)in any other case (except where the installation is included in the ultra-small emitter list for 2021-2025), must be treated as an application for a greenhouse gas emissions permit under paragraph 1 of Schedule 6 to this Order.

(2) An application under regulation 11 of GGETSR 2012 to vary a permit that is made to the regulator before 1st January 2021, but not determined before that date, must be treated as an application to vary the permit under paragraph 6 of Schedule 6 to this Order.

(3) An application under regulation 12 of GGETSR 2012 for the transfer of a permit that is made to the regulator before 1st January 2021, but not determined before that date, must be treated as an application to transfer the permit under paragraph 7 of Schedule 6 to this Order.

[F2(4) This sub-paragraph applies where—

(a)a permit for an installation is converted into a greenhouse gas emissions permit under paragraph 1(4);

(b)the monitoring methodology plan approved in respect of the installation under Article 8 of the Free Allocation Regulation is contained in the permit by virtue of paragraph 4(1)(hb) or (7) of Schedule 6; and

(b)a significant modification of the monitoring methodology plan is notified for approval under Article 9 of the Free Allocation Regulation on or before 31st December 2020, but not approved before that date.

(5) Where sub-paragraph (4) applies, the notification of the significant modification must be treated as an application to vary the permit under paragraph 6 of Schedule 6 to make the significant modification.]

Textual Amendments

Commencement Information

I2Sch. 11 para. 2 in force at 12.11.2020, see art. 2(1)

Schedule does not apply to permits for relevant Northern Ireland electricity generators, etc.U.K.

3.—(1) This Schedule does not apply to—

(a)relevant Northern Ireland permits; or

(b)applications for, or in relation to, relevant Northern Ireland permits.

(2) In this paragraph, “relevant Northern Ireland permit” means a permit within the meaning of GGETSR 2012 that authorises a regulated activity to be carried out at a relevant Northern Ireland electricity generator.

Commencement Information