1.—(1) In this Schedule—

“combustion unit” means a stationary technical unit in which fuels are combusted (and includes all types of boiler, burner, turbine, heater, furnace, incinerator, calciner, kiln, oven, dryer, engine, fuel cell, chemical looping combustion unit, flare and thermal or catalytic post-combustion unit);

“hazardous waste” means—

(a)

in relation to an installation in Northern Ireland or UK coastal waters adjacent to Northern Ireland, hazardous waste for the purposes of regulation 6 of the Hazardous Waste Regulations (Northern Ireland) 2005(1);

(b)

in relation to an installation in Scotland or UK coastal waters adjacent to Scotland, special waste within the meaning of regulation 2 of the Special Waste Regulations 1996(2);

(c)

in relation to an installation in Wales or UK coastal waters adjacent to Wales, hazardous waste for the purposes of regulation 6 of the Hazardous Waste (Wales) Regulations 2005(3);

(d)

in any other case, hazardous waste for the purposes of regulation 6 of the Hazardous Waste (England and Wales) Regulations 2005(4);

“municipal waste” has the meaning given in section 21(3) of the Waste and Emissions Trading Act 2003(5).

(2) For the purposes of this Schedule, a combustion unit or installation that uses only biomass as a fuel includes a combustion unit or installation that uses fossil fuels only during start-up or shut-down of operations.

Meaning of installation

2.—(1) Subject to sub-paragraph (2), in this Order, “installation” means a stationary technical unit or units where one or more regulated activities are carried out.

(2) “Installation” does not include any of the following (which are outside the scope of the UK ETS)—

(a)an installation that uses only biomass as a fuel;

(b)an installation, or part of an installation, the primary purpose of which is research and development (including the testing of new products and processes);

(c)an installation, the primary purpose of which is the incineration of hazardous or municipal waste;

(d)a relevant Northern Ireland electricity generator.

(3) In sub-paragraph (2), a reference to an installation is a reference to what would be an installation, but for that sub-paragraph.

(4) References in this Order to an installation include references to part of an installation.

Meaning of regulated activity, etc.

3.—(1) In this Order, “regulated activity” means—

(a)an activity set out in an entry in column 1 of table C that results in emissions of the gases set out in the corresponding entry in column 2; and

(b)where such an activity is carried out on a site, the combustion of fuels in any combustion unit (including a combustion unit referred to in sub-paragraph (5)(a) or (b)) operated on the site that results in emissions of such gases, except for a combustion unit to which sub-paragraph (2) applies.

(2) This sub-paragraph applies to a combustion unit if—

(a)the primary purpose of the unit is the incineration of hazardous or municipal waste; and

(b)the unit does not exclusively serve the stationary technical unit or units where the activity referred to in sub-paragraph (1)(a) is carried out.

(3) But sub-paragraph (2) does not apply to a combustion unit that is a flare.

Table C

Column 1Column 2
ActivitiesGreenhouse gases
Combustion of fuels on a site where combustion units with a total rated thermal input exceeding 20 megawatts are operatedCarbon dioxide
Refining of mineral oilCarbon dioxide
Production of cokeCarbon dioxide
Metal ore (including sulphide ore) roasting or sintering, including palletisationCarbon dioxide
Production of pig iron or steel (primary or secondary fusion) including continuous casting, with a capacity exceeding 2.5 tonnes per hourCarbon dioxide
Production or processing of ferrous metals (including ferro-alloys) on a site where combustion units with a total rated thermal input exceeding 20 megawatts are operated (and “processing” includes processing in rolling mills, re-heaters, annealing furnaces, smitheries, foundries, coating and pickling)Carbon dioxide
Production of primary aluminiumCarbon dioxide
Perfluorocarbons
Production of secondary aluminium on a site where combustion units with a total rated thermal input exceeding 20 megawatts are operatedCarbon dioxide
Production or processing of non-ferrous metals (including production of alloys, refining and foundry casting) on a site where combustion units with a total rated thermal input (including fuels used as reducing agents) exceeding 20 megawatts are operatedCarbon dioxide
Production of cement clinker in rotary kilns with a production capacity exceeding 500 tonnes per day or in other furnaces with a production capacity exceeding 50 tonnes per dayCarbon dioxide
Production of lime or calcination of dolomite or magnesite in rotary kilns or in other furnaces with a production capacity exceeding 50 tonnes per dayCarbon dioxide
Manufacture of glass including glass fibre with a melting capacity exceeding 20 tonnes per dayCarbon dioxide
Manufacture of ceramic products by firing, in particular roofing tiles, bricks, refractory bricks, tiles, stoneware or porcelain, with a production capacity exceeding 75 tonnes per dayCarbon dioxide
Manufacture of mineral wool insulation material using glass, rock or slag with a melting capacity exceeding 20 tonnes per dayCarbon dioxide
Drying or calcination of gypsum or production of plaster boards and other gypsum products on a site where combustion units with a total rated thermal input exceeding 20 megawatts are operatedCarbon dioxide
Production of pulp from timber or other fibrous materialsCarbon dioxide
Production of paper or cardboard with a production capacity exceeding 20 tonnes per dayCarbon dioxide
Production of carbon black involving the carbonisation of organic substances such as oils, tars, cracker and distillation residues on a site where combustion units with a total rated thermal input exceeding 20 megawatts are operatedCarbon dioxide
Production of nitric acidCarbon dioxide
Nitrous oxide
Production of adipic acidCarbon dioxide
Nitrous oxide
Production of glyoxal and glyoxylic acidCarbon dioxide
Nitrous oxide
Production of ammoniaCarbon dioxide
Production of bulk organic chemicals by cracking, reforming, partial or full oxidation or by similar processes, with a production capacity exceeding 100 tonnes per dayCarbon dioxide
Production of hydrogen (H2) and synthesis gas by reforming or partial oxidation with a production capacity exceeding 25 tonnes per dayCarbon dioxide
Production of soda ash (Na2CO3) and sodium bicarbonate (NaHCO3)Carbon dioxide
Capture of greenhouse gases from other installations for the purpose of transport and geological storage in a storage siteCarbon dioxide
Transport of greenhouse gases by pipelines for geological storage in a storage siteCarbon dioxide
Geological storage of greenhouse gases in a storage siteCarbon dioxide

(4) For the purpose of calculating the production or other capacity set out in an entry in column 1 of table C, where more than one activity referred to in the entry is carried out on a site, the capacities of all such activities must be added together.

(5) For the purpose of calculating the total rated thermal input of combustion units operated on a site, the rated thermal input of all combustion units on the site must be added together, except for—

(a)combustion units with a rated thermal input below 3 megawatts;

(b)combustion units that use only biomass as a fuel.

(6) Where the carrying out of an activity referred to in paragraph (a) of sub-paragraph (1) (that is to say, an activity set out in an entry in column 1 of table C) falls within both—

(a)an entry that does not refer to a threshold expressed as total rated thermal input; and

(b)an entry that refers to such a threshold,

for the purpose of this Order, the reference to the activity in that paragraph must be treated as a reference to the activity falling within the entry referred to in paragraph (a) of this sub-paragraph.

(7) In this Order, “specified emissions” means, in relation to a regulated activity referred to in sub-paragraph (1), the emissions of the gases referred to in that sub-paragraph.

(1)

S.R. 2005/300, to which there are amendments not relevant to this Order.

(2)

S.I. 1996/972. The definition of “special waste” was substituted by regulation 2(3) of S.S.I 2004/112 and is substituted prospectively by regulation 7(4) of S.S.I. 2019/26 with effect from IP completion day.

(3)

S.I. 2005/1806. Regulation 6 was amended by regulation 3(5) of S.I. 2015/1417.

(4)

S.I. 2005/894, to which there are amendments not relevant to this Order.

(5)

2003 c. 33. Section 21(3) was amended by regulation 6(2)(b) of S.I. 2011/2499.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources