The Network Rail (Cambridgeshire Level Crossing Reduction) Order 2020

Access to works

12.—(1) Network Rail may, for the purposes of the authorised works—

(a)form and lay out means of access, or improve existing means of access, in the locations specified in columns (1) and (2) of Schedule 12 (access to works); and

(b)with the approval of the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as Network Rail reasonably requires for the purposes of the authorised works.

(2) If a highway authority fails to notify Network Rail of its decision within 28 days of receiving an application for approval under paragraph (1), that highway authority is deemed to have granted approval.