SCHEDULES

SCHEDULE 3Secretary of State to decide if an environmental impact assessment is required, without a screening direction application where the definition of “project” applies

Regulations 3, 5, 7 and 19 and Schedule 2

The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.