Search Legislation

The Greenhouse Gas Emissions Trading Scheme (Amendment) Order 2020

Status:

This is the original version (as it was originally made).

Schedule 6 amended (permits)

This section has no associated Policy Notes

38.—(1) Schedule 6 is amended as follows.

Paragraph 4 amended (greenhouse gas emissions permits: content of permit)

(2) In paragraph 4—

(a)after sub-paragraph (1)(h) insert—

(ha)the free allocation conditions (see sub-paragraph (6));

(hb)where a monitoring methodology plan has been approved in relation to the installation under Article 8 of the Free Allocation Regulation, the monitoring methodology plan;;

(b)in sub-paragraph (2)(b)—

(i)after “verified” insert “as satisfactory”;

(ii)after “submit the report” insert “(and the verification report)”;

(c)after sub-paragraph (5) insert—

(6) The free allocation conditions are the following conditions, which must be expressed to apply while the installation is an FA installation—

(a)a condition requiring the operator to monitor the activity level of the installation in accordance with—

(i)the Free Allocation Regulation; and

(ii)the monitoring methodology plan approved under Article 8 of the Free Allocation Regulation (including the written documentation of the procedures referred to in Article 8(3) of that Regulation);

(b)a condition requiring the operator, in accordance with the Activity Level Changes Regulation, to prepare an activity level report that is verified as satisfactory in accordance with the Verification Regulation 2018 and to submit the report (and the verification report) to the regulator on or before 30th June in the 2021 scheme year and on or before 31st March in each subsequent scheme year;

(c)a condition requiring the operator, if the installation has ceased operation, to notify the regulator on or before 31st December in the scheme year in which the cessation occurs or within 1 month of the cessation, whichever is later;

(d)any further conditions that the regulator considers necessary to give proper effect to the Free Allocation Regulation or the Activity Level Changes Regulation.

(7) Where, after the date of issue of, or conversion of a permit into, a greenhouse gas emissions permit, a monitoring methodology plan is approved in relation to an installation under Article 8 of the Free Allocation Regulation, the regulator must vary the permit under paragraph 6 so that it contains the monitoring methodology plan..

Paragraph 6 amended (variation of permits)

(3) In paragraph 6—

(a)after sub-paragraph (2)(c) insert—

(d)a failure by the operator to implement—

(i)a recommendation for improvement of the monitoring methodology plan as required by Article 9(2)(e) of the Free Allocation Regulation; or

(ii)a modification of the monitoring methodology plan requested by the regulator under Article 9(5)(d) of that Regulation.;

(b)in sub-paragraph (3) before paragraph (a) insert—

(za)paragraph 4(7) (adding monitoring methodology plan);.

Paragraph 7 amended (transfer of permits: application)

(4) In paragraph 7(5) for “8(a)” in both places substitute “8(1)(a)”.

Paragraph 8 amended (transfer of permits: contents of application)

(5) In paragraph 8 renumber the existing text as sub-paragraph (1) and insert after that sub-paragraph—

(2) Where the application is for the transfer or partial transfer of a greenhouse gas emissions permit for an installation that is an FA installation, the application must also contain—

(a)either—

(i)the new operator’s monitoring methodology plan in accordance with Article 8 of the Free Allocation Regulation; or

(ii)the new operator’s specification of the parts of the existing monitoring methodology plan that it is proposed be varied;

(b)in the case of an application for the partial transfer of the permit, the transferring operator’s specification of the parts of the existing monitoring methodology plan that it is proposed be varied.

(3) But sub-paragraph (2) does not apply if the application contains a statement by the new operator that the new operator renounces free allocation in respect of the transferred units..

Paragraph 9 amended (transfer of permits: grant of application)

(6) In paragraph 9—

(a)in sub-paragraph (1)—

(i)in paragraph (a) omit the final “and”;

(ii)in paragraph (b) for “paragraph).” substitute “paragraph); and”;

(iii)after paragraph (b) insert—

(c)where the application is for the transfer or partial transfer of a greenhouse gas emissions permit of an installation that is an FA installation, will be capable of complying with the free allocation conditions of the permit (including as varied under this paragraph).;

(b)after sub-paragraph (1) insert—

(1A) But sub-paragraph (1)(c) does not apply if the application contains a statement by the new operator that the new operator renounces free allocation in respect of the transferred units.;

(c)after sub-paragraph (5) insert—

(5A) Where a permit is cancelled under sub-paragraph (5)(b), the regulator must give notice to the registry administrator as soon as reasonably practicable..

Paragraph 11 amended (surrender of permits)

(7) In paragraph 11(6)(b) after “complied with” insert “or that there is no reasonable prospect of their being complied with”.

Paragraph 12 amended (revocation of permits)

(8) In paragraph 12—

(a)after sub-paragraph (3)(a)(i)(cc) insert—

(dd)the Free Allocation Regulation;

(ee)the Activity Level Changes Regulation.;

(b)in sub-paragraph (7)(b) after “complied with” insert “or that there is no reasonable prospect of their being complied with”.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

Policy Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources