Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
23. After Article 18 insert—
1. Where an application for free allocation is made by a new entrant under Article 5, the regulator must send the information set out in paragraph 2 to the UK ETS authority as soon as reasonably practicable.
2. The information is:
(a)details of the installation, including details of the greenhouse gas emissions permit in force;
(b)the information contained in the new entrant data report submitted with the application under Article 5;
(c)the historical activity levels (if any) determined under Article 17;
(d)the preliminary annual number of allowances to be allocated in respect of the installation and of each sub-installation separately, as calculated under Article 18;
(e)where the regulator has not, by virtue of Article 5(6)(c), determined historical activity levels or the preliminary annual number of allowances, the regulator's explanation;
(f)except where point (e) applies, the final annual number of allowances to be allocated in respect of each sub-installation of the installation:
(i)for the scheme year in the relevant allocation period in which the start of normal operation of the sub-installation occurs; and
(ii)where the historical activity level of the sub-installation has been determined under Article 17, for each subsequent scheme year in the relevant allocation period;
(g)except where point (e) applies, the final annual number of allowances to be allocated in respect of the installation for each scheme year in the relevant allocation period;
(h)whether or not a monitoring methodology plan has been approved in relation to the installation under Article 8.
3. The final annual number of allowances to be allocated in respect of a sub-installation for a scheme year is the preliminary annual number of allowances calculated under Article 18 multiplied by the reduction factor for the scheme year.
4. The final annual number of allowances to be allocated in respect of an installation for a scheme year is the sum of the final annual number of allowances to be allocated in respect of all sub-installations of the installation for the scheme year.
5. The UK ETS authority must as soon as reasonably practicable:
(a)assess the application for free allocation and, where relevant, the regulator's explanation under paragraph 2(e); and
(b)inform the regulator whether or not the application is valid.
6. Where the application is valid, the UK ETS authority must also:
(a)approve the final annual number of allowances, making any corrections to the historical activity levels, preliminary annual number of allowances and final annual number of allowances that the UK ETS authority considers appropriate; and
(b)inform the regulator of the matters referred to in point (a).
7. But where a monitoring methodology plan has not been approved in relation to the installation at the date on which the information set out in paragraph 2 is sent to the UK ETS authority, paragraph 6 applies only after the regulator informs the UK ETS authority that the monitoring methodology plan submitted to the regulator for approval has been approved and does not apply if the regulator informs the UK ETS authority that the monitoring methodology plan has been rejected.
8. The regulator must give notice to the operator of the installation of the following:
(a)whether or not the application is valid;
(b)if the application is not valid, the reasons why it is not valid.
9. Where the application is valid, the regulator must also give notice to the operator:
(a)of the final annual number of allowances approved under paragraph 6; or
(b)that a final annual number of allowances has not been approved because the monitoring methodology plan submitted to the regulator for approval has been rejected.
10. For the purpose of the calculations referred to in paragraphs 3 and 4, the number of allowances for sub-installations and installations must be expressed as the nearest integer, taking 0.5 as nearest to the previous integer.
11. For the purposes of this Article, the reduction factor for a scheme year set out in column 1 of table B is the value set out in the corresponding entry in column 2.
Column 1 Scheme year | Column 2 Reduction factor |
---|---|
2021, 2026 | 1 |
2022, 2027 | 0.978 |
2023, 2028 | 0.956 |
2024, 2029 | 0.934 |
2025, 2030 | 0.912 |
12. For the purposes of this Article, an application for free allocation is valid if:
(a)the application is one which may be made under this Regulation (see Article 2a); and
(b)the application is otherwise in accordance with this Regulation.”.
Commencement Information
I1Sch. 1 para. 23 in force at 31.12.2020 on IP completion day, see art. 2(2)(a)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: