SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 2ANCILLARY WORKS
I11
Works within the Order limits which have been subject to an environmental impact assessment recorded in the environmental statement comprising—
a
temporary landing places, moorings or other means of accommodating vessels in the construction and/or maintenance of the authorised development;
b
marking buoys, beacons, fenders and other navigational warning or ship impact protection works; and
c
temporary works for the benefit or protection of land or structures affected by the authorised development.